One-piece flow means each part moves to the next step as soon as it is done, instead of waiting for the whole batch. Every part gets the same amount of work. The difference is the waiting: in a batch, each part spends most of its time waiting for the others, so lead time grows with batch size. The worked example below shows how much, with the arithmetic.
Batch lead time = batch size × steps × cycle time · Flow lead time = (steps + batch size − 1) × cycle time
Both formulas assume equal cycle times at every step, no transport time and no changeovers. The example works under those same assumptions, and the last section covers what happens when they don't hold.
The worked example
This is an illustration. A small cell makes ten brackets through three steps: cut, drill and deburr. Each step takes 1 minute per bracket.
In a batch of 10
- Cut: all 10 brackets are cut before any move on. 10 × 1 minute = done at minute 10.
- Drill: starts at minute 10 and takes another 10 minutes, so it is done at minute 20.
- Deburr: starts at minute 20 and takes another 10 minutes, so it is done at minute 30.
Lead time for the ten: 30 minutes. The first finished bracket comes out at minute 21, because deburring can't start until minute 20 and the first one takes 1 minute. Check with the formula: 10 × 3 × 1 = 30 minutes.
In one-piece flow
- Bracket 1 is cut by minute 1, drilled by minute 2 and deburred by minute 3.
- While bracket 1 is being drilled, bracket 2 is being cut. From then on, one bracket leaves the cell every minute.
- Bracket 10 finishes 9 minutes after bracket 1: 3 + 9 = minute 12.
Lead time for the ten: 12 minutes. The first finished bracket comes out at minute 3. Check with the formula: (3 + 10 − 1) × 1 = 12 minutes.
The middle way: moving in fives
Often the realistic first step is a smaller transfer batch, not one piece. Say the brackets move in trays of five.
- Tray A: cut 0–5, drill 5–10, deburr 10–15.
- Tray B: cut 5–10, drill 10–15, deburr 15–20.
Lead time for the ten: 20 minutes. The first finished bracket comes out at minute 11, because tray A starts deburring at minute 10.
| Batch of 10 | Trays of 5 | One-piece flow | |
|---|---|---|---|
| Lead time for 10 brackets | 30 min (10 × 3 × 1) | 20 min (tray B finishes deburring) | 12 min ((3 + 10 − 1) × 1) |
| First finished bracket | minute 21 (deburr starts at 20, plus 1) | minute 11 (deburr starts at 10, plus 1) | minute 3 (1 minute per step × 3 steps) |
| Work content per bracket | 3 min | 3 min | 3 min |
The last row is the point. The work content is 3 minutes per bracket in all three cases. Everything else is waiting, and batch size decides how much waiting there is. This is the gap that process cycle efficiency measures, and it is the difference explained in cycle time vs lead time.
The quality difference
Suppose the cut step has a setting wrong, and the drill operator would notice the first time they try to drill a bad bracket.
- In a batch of 10: drilling doesn't start until all 10 are cut, so all 10 are bad before anyone sees one.
- In one-piece flow: the drill operator gets bracket 1 at minute 1. By the time they find the problem, the cutter has made one or two more. One or two bad brackets, not ten.
Flow makes problems visible at once, which is why it goes with jidoka. In a batch, the problem stays hidden until the whole batch is made.
What has to be true for flow to work
- Balanced steps. If drilling takes 2 minutes and the others 1, the drill is the bottleneck and paces the cell. Pieces pile up before it either way. A yamazumi chart shows how far off balance you are, and takt time tells you what pace to balance to.
- Short distances. One piece at a time only pays if the next step is within arm's reach or a few steps away. If parts travel across the building, move them in small batches first, and redesign the layout later.
- Quick changeovers. Long setups push people toward big batches to "make the setup worth it". SMED is usually what makes smaller batches affordable.
- Reliable equipment. In flow there is no pile to keep working from when a machine stops, so stops show up at once. That is uncomfortable, and useful. Track them with downtime tracking or OEE.
When batches still make sense
Some processes are batch processes by nature: an oven that bakes a full rack, a paint booth, a heat treatment. In those cases the aim is a batch no bigger than the process needs, with flow before and after it. A value stream map shows where the batches are and how much lead time each one adds, so you can choose which one to shrink first.
One-piece flow in Lean Day Toolkit
Lean Day Toolkit has no flow simulator. What it has are the measurements the example depends on. The takt calculator and the stopwatch for quick time studies stay free. The VA/PCE tool, which compares value-added time with lead time, is in the full version. In its glossary, the app sums up the gap like this: "A pallet that takes six hours to move and eleven minutes of real work is 3% PCE."