One-piece flow vs batches: a worked example of the lead-time difference

Ten parts, three steps, one minute each: 30 minutes in batches, 12 in one-piece flow. The arithmetic step by step, and what has to be true for it to work.

· 4 min read · Plapl Games

One-piece flow means each part moves to the next step as soon as it is done, instead of waiting for the whole batch. Every part gets the same amount of work. The difference is the waiting: in a batch, each part spends most of its time waiting for the others, so lead time grows with batch size. The worked example below shows how much, with the arithmetic.

Batch lead time = batch size × steps × cycle time · Flow lead time = (steps + batch size − 1) × cycle time

Both formulas assume equal cycle times at every step, no transport time and no changeovers. The example works under those same assumptions, and the last section covers what happens when they don't hold.

The worked example

This is an illustration. A small cell makes ten brackets through three steps: cut, drill and deburr. Each step takes 1 minute per bracket.

In a batch of 10

  1. Cut: all 10 brackets are cut before any move on. 10 × 1 minute = done at minute 10.
  2. Drill: starts at minute 10 and takes another 10 minutes, so it is done at minute 20.
  3. Deburr: starts at minute 20 and takes another 10 minutes, so it is done at minute 30.

Lead time for the ten: 30 minutes. The first finished bracket comes out at minute 21, because deburring can't start until minute 20 and the first one takes 1 minute. Check with the formula: 10 × 3 × 1 = 30 minutes.

In one-piece flow

  1. Bracket 1 is cut by minute 1, drilled by minute 2 and deburred by minute 3.
  2. While bracket 1 is being drilled, bracket 2 is being cut. From then on, one bracket leaves the cell every minute.
  3. Bracket 10 finishes 9 minutes after bracket 1: 3 + 9 = minute 12.

Lead time for the ten: 12 minutes. The first finished bracket comes out at minute 3. Check with the formula: (3 + 10 − 1) × 1 = 12 minutes.

The middle way: moving in fives

Often the realistic first step is a smaller transfer batch, not one piece. Say the brackets move in trays of five.

  1. Tray A: cut 0–5, drill 5–10, deburr 10–15.
  2. Tray B: cut 5–10, drill 10–15, deburr 15–20.

Lead time for the ten: 20 minutes. The first finished bracket comes out at minute 11, because tray A starts deburring at minute 10.

Batch of 10Trays of 5One-piece flow
Lead time for 10 brackets30 min (10 × 3 × 1)20 min (tray B finishes deburring)12 min ((3 + 10 − 1) × 1)
First finished bracketminute 21 (deburr starts at 20, plus 1)minute 11 (deburr starts at 10, plus 1)minute 3 (1 minute per step × 3 steps)
Work content per bracket3 min3 min3 min

The last row is the point. The work content is 3 minutes per bracket in all three cases. Everything else is waiting, and batch size decides how much waiting there is. This is the gap that process cycle efficiency measures, and it is the difference explained in cycle time vs lead time.

The quality difference

Suppose the cut step has a setting wrong, and the drill operator would notice the first time they try to drill a bad bracket.

Flow makes problems visible at once, which is why it goes with jidoka. In a batch, the problem stays hidden until the whole batch is made.

What has to be true for flow to work

When batches still make sense

Some processes are batch processes by nature: an oven that bakes a full rack, a paint booth, a heat treatment. In those cases the aim is a batch no bigger than the process needs, with flow before and after it. A value stream map shows where the batches are and how much lead time each one adds, so you can choose which one to shrink first.

One-piece flow in Lean Day Toolkit

Lean Day Toolkit has no flow simulator. What it has are the measurements the example depends on. The takt calculator and the stopwatch for quick time studies stay free. The VA/PCE tool, which compares value-added time with lead time, is in the full version. In its glossary, the app sums up the gap like this: "A pallet that takes six hours to move and eleven minutes of real work is 3% PCE."