How to find the bottleneck on a line, and what to do about it

The whole line runs at the speed of its slowest step. Time each station, divide by the people on it, compare with takt, and then protect, offload and check.

· 4 min read · Plapl Games

The bottleneck is the step on a line with the longest cycle time per person, and the whole line cannot produce faster than that step. To find it, time each station, divide by the number of people working there, and compare the result with takt time. A step slower than takt makes the line miss demand; to fix it, first stop the step from losing time, then move work off it.

Line output ≤ available time ÷ the slowest cycle time per person

Why one step sets the pace

Work moves through a line like water through a pipe: the narrowest point sets the flow. Speeding up any other step only makes a bigger pile in front of the bottleneck, or more waiting after it. Eliyahu Goldratt built his theory of constraints on this idea in his book The Goal. Its five focusing steps are: identify the constraint, exploit it, subordinate everything else to it, elevate it, and then look for the next one.

It also means an hour lost at the bottleneck is an hour lost for the whole line. An hour lost at another step often costs nothing, as long as there is work waiting in front of the bottleneck to keep it busy.

How to find it

  1. Look first. Walk the line. Work piles up in front of the bottleneck, and people after it wait. That is a strong clue, but check it: a pile can also come from a stop earlier in the shift.
  2. Time each station. Measure several real cycles at every station with a stopwatch, and use a typical value rather than the fastest. See how to do a time study.
  3. Divide by the people on it. A 54-second station with two people on it produces a part every 27 seconds. Compare stations per person, not per station.
  4. Compare with takt. Work out takt time for current demand. Any station slower than takt is a problem; the slowest one is the bottleneck.

A yamazumi chart shows the result at a glance: one stacked bar per station, with a line drawn across at takt.

A worked example

This example is made up: a small assembly and pack line, one shift.

StationMeasured cycle (s)PeoplePer person (s)Against takt (30 s)
Kit24124 ÷ 1 = 24Under
Assemble54254 ÷ 2 = 27Under
Test34134 ÷ 1 = 34Over, by 4 s
Pack22122 ÷ 1 = 22Under

Test is the bottleneck. At 34 seconds a unit, the line can make at most 25,200 ÷ 34 = 741 units a shift (741.2, rounded down), against demand of 840. That leaves 840 − 741 = 99 units short every shift, however hard kit, assembly and pack work.

If test stops for a 15-minute break with nobody covering, the line loses 900 ÷ 34 = 26 more units (26.5, rounded down). A 15-minute stop at pack, with space to hold the work, costs nothing, because pack takes 22 seconds against test's 34, so it has 34 − 22 = 12 seconds of spare time on every unit to catch up.

What to do about it, in order

1. Stop the bottleneck losing time

Before changing the work, make sure the bottleneck never stands idle. Stagger breaks so someone covers test. Keep a small buffer of assembled units in front of it so it never waits for work. Track every stop at test in a downtime log. Send no bad units to test: a unit that is going to fail anyway takes up test time that could have gone to a good one.

2. Move work off it

Look at what the tester does inside those 34 seconds. In this example, 5 seconds of it is printing and applying the serial label, which needs no test equipment. Moving it to pack gives:

The slowest station per person is now test at 29 seconds, under takt. Capacity becomes 25,200 ÷ 29 = 868 units a shift (868.97, rounded down), against demand of 840.

3. Only then add capacity

If moving work is not enough, cut the work content with a kaizen event or faster changeovers (SMED) at the bottleneck, and only then consider a second tester or another person. Adding people elsewhere on the line does nothing for output.

4. Check again

Once test is under takt, the bottleneck moves. Here, assemble and pack are now both at 27 seconds, close behind. Time the line again, and recalculate takt whenever demand changes. Post the hourly output on an hour-by-hour board so the team sees whether the change held.

Common mistakes

Bottlenecks in Lean Day Toolkit

In Lean Day Toolkit, the stopwatch for timing a station stays free, and so does the takt calculator. The line map draws stations and flows with a takt-colored load on each, and it treats the station with the highest time per operator as the bottleneck. After a kaizen event on the line, its report shows the bottleneck before and after. The line map and kaizen events are in the full version.