Line balancing with a yamazumi chart, with a worked example

Stack each station's timed steps, draw a line at takt, and the imbalance shows itself. A worked example, with every number shown, from four operators to three.

· 6 min read · Plapl Games

Line balancing means sharing the work across stations so each one finishes inside takt time and none of them stands waiting for long. A yamazumi chart shows how even the line is: one bar per station, stacked from the timed steps of the job, with a line drawn across at takt, so the bars above the line and the short bars both stand out. Yamazumi is Japanese for "piled up", which is exactly what the bars are.

Minimum operators = total work content ÷ takt time, rounded up

What you need before you draw it

A worked example

This is an illustration: a small assembly line with four stations and one operator at each. It runs one 8-hour shift and has to make 450 units a day.

  1. Time available: 8 hours is 480 minutes. Take out 30 minutes of planned breaks and that leaves 450 minutes, or 450 × 60 = 27,000 seconds.
  2. Takt: 27,000 seconds ÷ 450 units = 60 seconds a unit.

Each step below is the average of ten timed cycles, in seconds. The station total is the sum of its steps, and the last column is the station total minus the 60-second takt.

StationSteps (seconds)TotalAgainst 60 s takt
1 Kitkit parts 22 + walk to screw rack 123426 under
2 Fit and screwfit board 20 + drive screws 16 + search for driver 10 + connect and test 267212 over
3 Label and inspectlabel 12 + inspect 203228 under
4 Packfold box 20 + pack and seal 24 + carry to pallet 14582 under
Line34 + 72 + 32 + 58196work content

Drawn as a chart, station 2 is the one bar sticking up through the takt line. That makes it the bottleneck, and the line can't go faster than it: 27,000 seconds ÷ 72 seconds = 375 units a shift, against 450 needed. That leaves the line 75 units short every day. Meanwhile stations 1 and 3 wait 26 and 28 seconds every cycle for work to arrive.

Step 1: how many people does the work need?

Total work content is 196 seconds. 196 ÷ 60 = 3.27, which rounds up to 4. So four operators is the right number for the job as it stands today. The problem is how the work is shared out, not how many people are doing it.

Step 2: move work to the short bars

"Connect and test" is the last step at station 2, so it can move to station 3, which is next in the sequence, without breaking the order. Station 2 drops to 72 − 26 = 46 seconds. Station 3 goes up to 32 + 26 = 58 seconds. Stations 1 and 4 stay at 34 and 58.

Every bar is now under the line. The slowest stations are 3 and 4 at 58 seconds, so the line can make 27,000 ÷ 58 = 465.5, which is 465 whole units a shift. That covers the 450. One way to score the balance is work content ÷ (operators × takt): 196 ÷ (4 × 60) = 196 ÷ 240 = 81.7%. The other 18.3% is waiting time built into the line.

Step 3: take the waste out before you share the work again

Two of the steps add nothing: walking 12 seconds to the screw rack, and 10 seconds hunting for the driver. Put the screws at the bench where they are used and hang the driver on a shadow board at station 2, and 12 + 10 = 22 seconds go. Work content falls to 196 − 22 = 174 seconds, and 174 ÷ 60 = 2.9, which rounds up to 3 operators.

Step 4: rebalance for three

StationSteps (seconds)Total
Akit parts 22 + fit board 20 + drive screws 1658
Bconnect and test 26 + label 12 + inspect 2058
Cfold box 20 + pack and seal 24 + carry to pallet 1458
Line58 + 58 + 58174

The steps keep their order, each station is 2 seconds under takt, and the balance is now 174 ÷ (3 × 60) = 174 ÷ 180 = 96.7%. The fourth operator is free to go where they are needed, such as the next bottleneck or the improvement work itself.

Before you make it the standard, look at that margin. Two seconds is 3.3% of takt, and one fumbled screw puts a station over the line. Run the new layout for a few shifts with an hour-by-hour board and see whether it holds. If it doesn't, four people on a better-balanced line is still a good result.

Five rules that keep the chart honest

1. Balance against takt, not against each other

Making the bars equal is not the goal. The goal is every bar under the takt line with as little waiting as possible. A perfectly even line that sits over takt still ships late.

2. Take out waste first

If you move a walk or a search to another station, you are just passing the waste along. Look for the eight wastes in each stack and remove them before you share the work again.

3. Respect the sequence and the equipment

The minimum-operators sum assumes any step can go anywhere. Real lines have fixtures, machines and an order the steps must follow. Treat the sum as a floor you may not reach, not a promise.

4. Watch the spread, not just the average

A step that averages 20 seconds but sometimes takes 35 will push its station over takt. If the time study shows a wide spread, make the step stable first. Otherwise you are balancing numbers the floor doesn't actually hit.

5. Redraw it when takt changes

Demand moves, so the takt line moves with it. A line balanced for 450 a day is out of balance at 520. Recalculate takt, redraw the line on the chart, and check the bars again.

Yamazumi charts in Lean Day Toolkit

Lean Day Toolkit draws a yamazumi chart from the line map, under Floor → Line map, in the full version of the app. You set takt by entering the available time per shift and the demand per shift, and every station bar gets a takt mark. A station with an accepted step-by-step study is stacked from its steps. A station with only a typed standard time shows as one block, labeled as having no breakdown. The chart lists the line's work content, the bottleneck station, the theoretical minimum operators (work content ÷ takt, rounded up, with a note that it ignores sequence and machine constraints) and the projected output per shift. Inside a kaizen event, a Rebalance screen lets you move work between stations and watch the load change, and save the result as a scenario without touching the live line. The line map's PDF prints the same yamazumi chart.