Autonomous maintenance is the part of total productive maintenance (TPM) in which the people who run a machine clean it, inspect it and lubricate it every day, using a short standard check that they own. Maintenance keeps the repairs and the specialist work, and operators catch the loose bolt, the leak and the dry chain before any of them becomes a breakdown.
Clean → inspect while you clean → lubricate → tag what's wrong → fix it or hand it on
Where it comes from
TPM was developed in Japan in the 1970s and is most closely tied to Seiichi Nakajima and the Japan Institute of Plant Maintenance (JIPM). Autonomous maintenance (jishu hozen) is one of its pillars. The idea behind it is simple: the operator is at the machine all shift and notices things maintenance never will, such as a new noise, a drip or a hot smell. TPM gives operators the routine and the skills to act on what they notice.
The key phrase is cleaning is inspection. When you wipe a machine down by hand, you touch every bolt, hose and guard, and that is when you find the crack.
The seven steps
JIPM's version of autonomous maintenance has seven steps. Most sites spend months on the first three before going any further.
- Initial cleaning. Operators and maintenance clean the machine thoroughly together and tag every problem they find.
- Fix sources of contamination and hard-to-reach places. Stop the leak, fit a guard against the swarf, and make the dirty spot easy to reach.
- Set cleaning and lubrication standards. Write down what gets cleaned and lubricated, how, and how often, and how long it should take.
- General inspection. Train operators on how the machine works, so they know what "wrong" looks like.
- Autonomous inspection. Operators run the inspection check themselves, every shift.
- Standardization. Organize the area and the check so they hold, much like 5S.
- Autonomous management. The team improves its own machine and its own check.
An example daily check card
This is an illustration: a daily check for a case packer, written by the team after their initial clean. The standards come from the machine maker's manual, and the times are what the team measured when they did each item at a normal pace.
| # | Item | How | Standard | Seconds |
|---|---|---|---|---|
| 1 | Glue nozzle area | Wipe with a cloth | No glue build-up | 120 |
| 2 | Drive chain tension | Press at the midpoint | 10–15 mm of give | 45 |
| 3 | Drive chain lubrication | Oil from the marked can, wipe off the surplus | Wet, not dripping | 60 |
| 4 | Air pressure | Read the gauge | 80–90 psi (green band) | 15 |
| 5 | Guards | Look | All fitted, no bolts missing | 30 |
| 6 | Leaks and noise | Look under the machine, listen | No drips, no new noise | 45 |
| 7 | Suction cups and belts | Look | No tears or cracks | 60 |
| 8 | Floor under the machine | Sweep, look at what you swept | No loose parts | 120 |
Add up the seconds column: 120 + 45 + 60 + 15 + 30 + 45 + 60 + 120 = 495 seconds, or 8 minutes 15 seconds. The machine runs two shifts a day, five days a week, so that is 10 checks a week, and 10 × 8.25 minutes = 82.5 minutes a week. Compare that with the downtime from one unplanned chain failure on your own line; your downtime log will tell you what that costs.
Item 8 matters more than it looks. A bolt on the floor came from somewhere on the machine.
What makes a card work
- A photo for each item. Show the nozzle clean, the gauge in the green and the oil point marked. A visual standard does this better than words.
- Short. Ten minutes or less. A check that takes half an hour gets skipped on a busy day, and busy days are when it matters most.
- Marked on the machine. Color the lubrication points, put a green band on the gauge and add a match mark on the critical bolts so a loose one shows at a glance.
- Clear limits. The card says what operators do, such as wiping, oiling, reading and tightening a marked guard bolt with the wrench on the shadow board. Anything electrical, and any adjustment that isn't on the card, goes to maintenance.
Safety first
Cleaning near moving parts is where people get hurt. Anything inside a guard is done with the machine isolated, under your site's lockout/tagout procedure. In the US, OSHA's standard on the control of hazardous energy (29 CFR 1910.147) covers this. Write the isolation step on the card as item zero. If you find a hazard during the check, report it like any other near miss.
What happens to a problem
An operator who finds something wrong either fixes it, if it is on the card, or tags it and writes it up for maintenance. The tag stays on the machine until the fix is done, so everyone walking past can see it. Review open tags at the daily meeting or on the SPQDC board. If a tag comes back again and again, run a 5 Whys on it.
The fastest way to kill autonomous maintenance is to let tags sit for weeks. Operators stop writing them, and the check turns into a cleaning chore.
How to start
- Pick one machine that the team cares about, usually the one that stops most.
- Do the initial clean together, with maintenance there, and tag everything you find.
- Fix the tags and the sources of dirt before you ask anyone to keep the machine clean.
- Write the card with the team, time each item, and post it at the machine.
- Have the supervisor check that the card was done, as part of leader standard work.
- Watch the stops. OEE and the six big losses show whether breakdowns and minor stops are falling.
Daily machine checks in Lean Day Toolkit
Lean Day Toolkit has an equipment register for machines, trucks, benches and racks, in the full version of the app. A checklist can belong to one piece of equipment, so a run asks which machine it is for. The template packs include a pass/fail forklift pre-use check, "Daily, per truck, before the first lift." A check can be scheduled daily, weekly or monthly, and a missed check is filed as a tracked action. Any item that fails becomes an action by itself, on the action list, which stays free.