The six big losses are the six ways a machine or line loses planned production time: breakdowns, setups and adjustments, small stops, reduced speed, startup rejects and production rejects. Each one pulls down one of the three OEE factors, so if you put minutes against all six you can see which loss is costing you the most capacity. The list comes from Total Productive Maintenance (TPM), which Seiichi Nakajima set out for the Japan Institute of Plant Maintenance.
OEE = availability × performance × quality, and every point lost below 100% is one of six losses
The six losses, grouped by factor
If OEE is new to you, start there. The six losses split it into causes you can act on:
| OEE factor | Loss | What it looks like |
|---|---|---|
| Availability | 1. Breakdowns | The machine stops and needs a repair: a motor trips or a belt snaps. |
| 2. Setups and adjustments | Changeovers, warm-up and fiddling until the first good part comes off. | |
| Performance | 3. Small stops | Stops of a minute or two that the operator clears: a jammed carton or a blocked sensor. |
| 4. Reduced speed | The machine runs, but slower than its rated speed. | |
| Quality | 5. Startup rejects | Scrap and rework made while the line settles after a start or a changeover. |
| 6. Production rejects | Scrap and rework made during steady running. |
Losses 3 and 4 are the ones nobody writes down. A breakdown gets a call to maintenance. A 40-second jam cleared by hand gets nothing, and fifty of them in a shift can cost more than the breakdown did.
A worked example
This example is made up, with small, realistic numbers: one shift on a case packer.
- The shift is 480 minutes, with 30 minutes of planned breaks, which leaves 450 minutes of planned production time.
- The rated (ideal) cycle is 30 seconds a case, which is 2 cases a minute.
- The line packed 640 cases, and 608 of them were good.
Availability: losses 1 and 2
The downtime log shows one breakdown of 25 minutes and one changeover of 35 minutes.
- Stopped time: 25 + 35 = 60 minutes.
- Run time: 450 − 60 = 390 minutes.
- Availability: 390 ÷ 450 = 0.867, or 86.7%.
Performance: losses 3 and 4
- At 2 cases a minute, 390 minutes of running should have made 390 × 2 = 780 cases.
- The line made 640, so performance is 640 ÷ 780 = 0.821, or 82.1%.
- The gap is 780 − 640 = 140 cases. At 30 seconds each, that is 140 × 0.5 = 70 minutes of lost running.
To split those 70 minutes, the team leader kept a tally of small stops for the shift: 52 stops, averaging about 45 seconds each. 52 × 45 = 2,340 seconds, which is 39 minutes of small stops. The other 70 − 39 = 31 minutes is reduced speed: the packer was running, just below its rated speed.
Quality: losses 5 and 6
- Rejects: 640 − 608 = 32 cases. Of those, 12 came in the first minutes after the changeover (startup) and 20 during steady running (production).
- Quality: 608 ÷ 640 = 0.95, or 95.0%.
- In time: 12 × 0.5 = 6 minutes of startup rejects, and 20 × 0.5 = 10 minutes of production rejects.
OEE
0.867 × 0.821 × 0.95 = 0.676, so OEE is 67.6%. To check it another way, take the good cases at the rated cycle: 608 × 30 seconds = 18,240 seconds, or 304 minutes. 304 ÷ 450 = 0.676, the same answer.
The six losses in minutes
Putting every loss in minutes lets you compare them directly.
| Loss | Minutes | Where the number came from |
|---|---|---|
| Small stops | 39 | 52 stops × 45 s = 2,340 s |
| Setups and adjustments | 35 | One changeover, from the downtime log |
| Reduced speed | 31 | 70 min of performance loss − 39 min of small stops |
| Breakdowns | 25 | One breakdown, from the downtime log |
| Production rejects | 10 | 20 cases × 0.5 min |
| Startup rejects | 6 | 12 cases × 0.5 min |
| Total lost | 146 | 25 + 35 + 39 + 31 + 6 + 10 |
| Good time | 304 | 450 planned − 146 lost; 304 ÷ 450 = 67.6% OEE |
The breakdown is the loss everyone remembers from this shift, but it comes fourth. The 52 small stops cost more time than either the breakdown or the changeover. Drawn as a Pareto chart, small stops and the changeover together make up 74 of the 146 lost minutes, or about half.
How to find each loss on the floor
- Breakdowns: start a clock the moment the line stops and record what got it running again. That record is a downtime log.
- Setups and adjustments: time a changeover from the last good part of one product to the first good part of the next, not until the machine restarts. The adjusting time belongs to the setup. SMED is the method for cutting it.
- Small stops: for one shift, keep a tally sheet at the machine and make one mark per stop. Most logs miss them because no one writes down a 40-second stop.
- Reduced speed: compare the rated cycle with a cycle you measure yourself. A short time study at the machine is enough. Find out who slowed it down and why; there is often an old quality problem behind it.
- Startup rejects: keep scrap from the first minutes after a start in a separate bin, so you can count it apart from the rest.
- Production rejects: count what fails during steady running, and include rework, because a reworked part was not right first time. See first pass yield.
An hour-by-hour board shows when in the shift the gap opens, which narrows the search. Once you know which loss is largest, a 5 Whys on that loss is usually the next step.
Common mistakes
- Counting setups as planned time. If you take changeovers out of planned time, the setup loss disappears from OEE and nobody works on it.
- Using a slowed-down "standard" as the ideal cycle. Use the rated speed, or the fastest the machine has reliably run. If you use the slower figure, the reduced-speed loss disappears from the numbers.
- Measuring once. One shift is a snapshot. Track the six losses for a few weeks before you decide which one to fix.
The six big losses in Lean Day Toolkit
Lean Day Toolkit has an OEE calculator under Tools → OEE, and it is one of the tools that stays free. You enter the shift length, planned and unplanned stops, the ideal cycle, the total made and the good count. It shows OEE against the 85% world-class mark, breaks it into availability, performance and quality, and names the weakest factor. The downtime log and the hour-by-hour board, where the minutes come from, are in the full version.