SMED cuts changeover time by sorting every step of a changeover into internal work, which can only be done with the line stopped, and external work, which can be done while the line is still running. You move the external work out of the stop, then shorten what is left, and in the worked example below a filler changeover goes from 52 minutes to 22.
Changeover time = last good unit of the old run → first good unit of the new run
Where it comes from
SMED stands for Single-Minute Exchange of Die. Shigeo Shingo developed it from the 1950s onward, working with Toyota and other Japanese manufacturers, and described it in his book A Revolution in Manufacturing: The SMED System. "Single-minute" means a single-digit number of minutes, so under ten. The die was a press die, but the method works on any changeover: a filler changing bottle size, a printer changing labels, a mold change, a packing line changing cartons.
Shingo's method has three stages. Separate internal from external work. Convert internal work to external wherever you can. Then streamline whatever is still internal. Most of the early gain comes from the first two, and they cost almost nothing.
Measure the changeover as it is
Changeover time runs from the last good unit of the old product to the first good unit of the new one. That includes the fiddling, the trial runs and the first-off check, not just the time wrenches are turning. A changeover "done" at 30 minutes that makes scrap for another 15 is a 45-minute changeover.
Time it at the job, step by step, and write down every step, including the walking and the waiting. Filming it helps, because the people doing it can watch it back with you. Time more than one changeover if you can, because one is an anecdote. The time study article covers how to time steps.
Internal or external: one question
For each step, ask: could this be done while the line is still running the old product?
- Yes: it is external. Fetching parts, finding tools, bringing the new labels and paperwork, preheating, and checking the next job's parts are usually external, even if today they happen with the line stopped.
- No: it is internal. Removing the old parts, fitting the new ones and the first-off check need the line stopped.
Answer from what you saw, not from habit. "We always do it that way" is not a reason a step needs the line stopped.
A worked example: a filler changeover
A bottle filler changes from one bottle size to another. The team timed three changeovers. The numbers below are an illustration: the minutes are the average for each step across the three, and every step was being done with the line stopped.
| Step | Minutes | Needs the line stopped? |
|---|---|---|
| 1. Find and fetch change parts from the store | 8 | No: external |
| 2. Fetch the tool cart | 4 | No: external |
| 3. Remove old guide rails and star wheels | 6 | Yes: internal |
| 4. Clean the product contact parts | 7 | Yes: internal |
| 5. Fit the new parts | 9 | Yes: internal |
| 6. Wait for the new labels and spec sheet | 5 | No: external |
| 7. Set heights by trial and adjustment | 10 | Yes: internal |
| 8. First-off check and sign-off | 3 | Yes: internal |
| Total, line stopped | 52 |
Here is the arithmetic for the first two stages:
- Today's changeover: 8 + 4 + 6 + 7 + 9 + 5 + 10 + 3 = 52 minutes, all with the line stopped.
- The external steps: 8 + 4 + 5 = 17 minutes. None of them needs the line stopped.
- Move them before the stop: stage the parts, the tool cart, the labels and the spec sheet at the filler while the last run finishes. The line is now down for 52 − 17 = 35 minutes. Check: 6 + 7 + 9 + 10 + 3 = 35.
- The saving so far: 17 ÷ 52 = 32.7% of the changeover, with no new equipment.
Then shorten the internal steps
The 35 minutes left all need the line stopped, so the next job is to make each of them shorter. Look for adjustment, fasteners and searching:
- Step 7, setting heights by trial (10 minutes): mark the correct setting for each bottle size on the machine, or use a gauge block, so the first setting is the right one. Target: 3 minutes.
- Steps 3 and 5, removing and fitting (6 and 9 minutes): replace bolts with quick-release clamps on the guide rails. Target: 3 minutes to remove and 6 to fit.
- Steps 4 and 8, cleaning and the first-off check (7 and 3 minutes): left as they are for now.
With those targets the line is down for 3 + 7 + 6 + 3 + 3 = 22 minutes: removing 3, cleaning 7, fitting 6, setting 3 and checking 3. From 52 minutes that is 52 − 22 = 30 minutes saved, and 30 ÷ 52 = 57.7% of the original changeover. These are targets until you time the new method, so time the next three changeovers and use the real numbers.
The 17 minutes of external work don't disappear. Someone still fetches the parts. But they do it while the line is making product, so the total hands-on work is 22 + 17 = 39 minutes while the line is only down for 22.
What the minutes buy
If the filler changes over six times a week, the saving is 30 × 6 = 180 minutes, or 3 hours of running time a week. You can spend that two ways: run more, or change over more often and make smaller batches that follow demand more closely. Shorter changeovers are what make small batches affordable.
Changeover time is lost running time, so it shows up in the availability part of OEE. If your downtime log has a "changeover overrun" category, that is a good place to find the first changeover to work on.
Make the new method the standard
- Write a changeover checklist in two parts: what is staged before the line stops, and what is done while it is stopped, in order. The 5 Whys example ends with a setting missing from a changeover checklist; a checklist is only as good as what is on it.
- Make it visual: a shadow board on the tool cart, labeled change parts, marked settings. See visual standards.
- Keep timing it: put changeover minutes on the hour-by-hour board so an overrun gets noticed the same day.
Common mistakes
- Starting with new equipment. Moving external work out of the stop is free. Do it first.
- Stopping the clock too early. The changeover ends at the first good unit, not when the guards go back on.
- Doing it without the people who do the changeover. They know where the time goes, and they are the ones who will run the new method.
- Not writing it down. A faster changeover that lives in one person's head goes back to 52 minutes when they are on vacation.
SMED in Lean Day Toolkit
Lean Day Toolkit has SMED in the full version of the app. You time the changeover as a step-by-step time study, or from a video of it, and open SMED from the study's result. Each step gets one of three marks: STOPS LINE, OFF-LINE or CAN MOVE, where CAN MOVE is a step done with the line stopped today that could be done while it runs. A step you haven't marked counts as line-down time, and so do interruptions during the changeover. The screen shows how long the line would be down once the movable steps are moved. One button raises each movable step as a tracked action, biggest first, with the biggest set to high priority. Step times are averages across the changeovers you timed, so time more than one.