First pass yield (FPY) is the share of units that come through one step right the first time, with no rework and no scrap: units good first time divided by units that went in. Rolled throughput yield (RTY) is the chance that a unit gets through every step right the first time, and you get it by multiplying the first pass yields of all the steps together. Both numbers show the rework that a plain "good out ÷ started" yield hides.
FPY = units good first time ÷ units in · RTY = FPY1 × FPY2 × … × FPYn
Why final yield isn't enough
Most sites already track some form of final yield: good units shipped divided by units started. It counts scrap, but it doesn't count rework. A part that was welded, rejected, ground back and welded again counts as good. On the report it looks the same as a part that was right the first time, but it used twice the welding time.
That repair work is sometimes called the "hidden factory": people, time and floor space spent doing jobs twice. First pass yield brings it into view, one step at a time.
A worked example
This is an example, not real data. A small fabrication line has three steps: cut, weld and paint. On Monday it starts 500 brackets. At each step the team leader counts three things: how many brackets went in, how many were good the first time, and how many were scrapped. Whatever is left over was reworked and then passed.
| Step | In | Good first time | Reworked | Scrapped | Out | FPY |
|---|---|---|---|---|---|---|
| Cut | 500 | 470 | 20 | 10 | 490 | 94.0% |
| Weld | 490 | 451 | 29 | 10 | 480 | 92.0% |
| Paint | 480 | 456 | 19 | 5 | 475 | 95.0% |
How to read the table. In is what reached the step. Good first time was counted at the step. Reworked is in − good first time − scrapped (cut: 500 − 470 − 10 = 20). Out is in − scrapped, because reworked brackets go on to the next step (cut: 500 − 10 = 490). Each step's out is the next step's in. FPY is good first time ÷ in.
Step 1: first pass yield at each step
- Cut: 470 ÷ 500 = 0.940, or 94.0%.
- Weld: 451 ÷ 490 = 0.9204, or 92.0%.
- Paint: 456 ÷ 480 = 0.950, or 95.0%.
Step 2: rolled throughput yield
- Multiply the first two: 0.940 × 0.9204 = 0.8652.
- Multiply by the third: 0.8652 × 0.950 = 0.8219.
- RTY = 82.2%.
Out of every 100 brackets started, only about 82 get through all three steps without anything being done twice.
Step 3: compare it with final yield
Final yield is 475 shipped ÷ 500 started = 0.950, or 95.0%. That looks healthy. But the reworked column adds up to 20 + 29 + 19 = 68 brackets that were handled twice somewhere on the line. The 95% shows the scrap. The 82.2% also shows the repairs.
What to do with the numbers
- Start at the lowest step. Here it is weld, at 92.0%. It also has the most rework, 29 brackets. That is where an hour of problem solving pays back first.
- Sort the reasons. Ask the welders to tally why each bracket was reworked, then put the tallies on a Pareto chart. Usually one or two reasons cover most of the count.
- Find the cause of the biggest one. Use a 5 Whys at the welding bay, not in the office. If the cause is something easy to get wrong, such as a part that fits the jig both ways round, a poka-yoke may stop it for good.
- Track it daily. A weekly FPY figure is too late to remember what went wrong on Tuesday. The quality line of an SPQDC board or an hour-by-hour board is a good home for it.
First pass yield and OEE
If you already calculate OEE, its quality factor is close to first pass yield for one machine: good parts made first time divided by total parts made. The difference is scope. OEE quality looks at one machine, while RTY follows the product through the whole line, so it shows where losses stack up from step to step.
Common mistakes
1. Counting reworked units as good first time
This is the mistake that makes FPY the same as final yield. If a unit went back, even for thirty seconds, it is not good first time. Agree with the team what counts as rework before you start counting. Touch-ups, re-tests and "just a quick adjust" all count.
2. Averaging instead of multiplying
The average of 94.0%, 92.0% and 95.0% is 93.7%. That is not the chance of getting through all three steps. Losses compound, so multiply. The more steps a line has, the further RTY falls below any single step's yield.
3. Using the wrong denominator
Divide by what went into the step, not by what the line started. Weld's FPY is 451 ÷ 490, not 451 ÷ 500, because ten brackets were already scrapped at cut.
4. Blaming the step with the low number
A low yield at paint can start with burrs left at cut. Look upstream as well, and treat the numbers as a question about the process, not a grade for the people at that step.
Yield in Lean Day Toolkit
Lean Day Toolkit has no first pass yield calculator. The OEE calculator works out availability, performance and quality for one machine, and it is one of the tools that stays free. The 5 Whys stays free too, and its chain ends as a tracked action. In the full version, the defects tool lets you mark each defect on a recording and export the video.