How to run a kaizen event: a plan for the week

One process, one target with a number, one team, one week on the floor. What to do before, each day of the event, and in the 30 days after.

· 5 min read · Plapl Games

A kaizen event is a short, focused improvement project, usually three to five days long, in which a small team works full time on one process and changes it on the floor that same week. Most of the result depends on the preparation before the week and the follow-up after it, so this plan covers the two weeks before, five days on the floor, and the 30 days after.

Prepare → understand → find causes → try changes → standardize → report out → follow up at 30 days

What a kaizen event is for

Kaizen is Japanese for "change for the better", usually translated as continuous improvement. Masaaki Imai brought the word to a wide Western audience with his 1986 book Kaizen: The Key to Japan's Competitive Success. Everyday kaizen is small changes made all the time. An event packs the same idea into one week, for a problem too big for a quick fix but small enough to change in a few days.

It is not the place for a problem nobody understands yet. If you don't know what is causing it, start with an A3 and run the event once you do.

Two weeks before: prepare

A worked target

Here is how a target might be set for a packing cell. The numbers are an illustration.

  1. Time available: one shift has 435 minutes of production time, which is 435 × 60 = 26,100 seconds.
  2. Demand: 470 cartons a shift.
  3. Takt time: 26,100 ÷ 470 = 55.5 seconds a carton. (See how to calculate takt time.)
  4. Today: the slowest station was timed at 64 seconds, so the cell can finish at most 26,100 ÷ 64 = 407.8, which is 407 full cartons a shift.
  5. The gap: 470 − 407 = 63 cartons a shift short.

So the target is: every station at or under 55 seconds by Friday, with the same number of people. One number everyone can check with a stopwatch.

The week, day by day

DayFocusDone by the end of the day
MondayUnderstandThe team knows the basics, has walked the process and has checked the baseline
TuesdayFind the causesWaste marked on each step, causes found, ideas listed and sorted
WednesdayTry changesThe first changes made on the floor and timed
ThursdayRefine and standardizeWhat worked is kept and written down; what didn't is dropped
FridayReport outResults against the target, a 30-day action list, thanks

Monday: understand

Spend the morning on a short introduction: the target, takt, the eight wastes and how to time a step. In the afternoon, go to the floor. Do a gemba walk along the process and time each station yourselves rather than trusting the report. If the baseline is wrong, better to know on Monday.

Tuesday: find the causes

List each step and mark the waste in it: walking, waiting, reaching, rework. At the biggest losses, ask why until you reach something you can change, using the 5 Whys. Collect every idea, then sort them on a PICK chart by impact and effort so Wednesday starts with the easy wins.

Wednesday: try changes

Make the changes on the floor, not on paper. Move the bench, change the sequence, build a fixture out of cardboard before anyone orders steel. Time each change. Some ideas will fail, and that is what Wednesday is for. Keep every safety guard and quality check in place while you experiment.

Thursday: refine and standardize

Keep what worked and drop what didn't. Write the new method as standard work, put up visual standards, and show the people on the other shift. Take the "after" photographs for your before-and-after sheets.

Friday: report out

Hold the report-out on the floor, 20 to 30 minutes, with the team presenting. Show the result against the target on one number. The Ideas poster puts it as Before and after, on one number. That is what makes it real. If the slowest station is now 52 seconds, the cell can finish 26,100 ÷ 52 = 501.9, so 501 full cartons a shift: enough for the 470, with room for small stops. Then go through what is still open, and thank people by name.

The 30 days after

Few events finish everything. The leftovers become a 30-day action list: each item with one owner and a date, reviewed every week, for example at the SPQDC board. At 30 days, time the process again. If the number has slipped back, find out why: usually the standard isn't being followed, or it was never quite workable. Building a check into leader standard work keeps the gain from fading.

Common mistakes

Kaizen events in Lean Day Toolkit

Lean Day Toolkit has kaizen events in the full version of the app, on the line map. An event belongs to one line and holds what it is for, who is on it and an agenda by day. You can give it its own demand and available time per shift, or leave them empty and use the line's own takt. Starting the event freezes a baseline of the line that is never edited afterward, so Monday's numbers are still there on Friday. While it runs, what you log at a station on that line, such as waste, ideas, actions and studies, is tagged to the event. A rebalance screen lets you move work between stations and save scenarios without touching the live line. The event pack puts the baseline against now, the agenda, what was captured and who took part into one PDF.