A before and after sheet shows one improvement on one page: a photograph of the place as it was, a photograph from the same spot after the change, one sentence on what was done, and the number that moved. If there is no result to measure yet, the sheet names who owns the follow-up and by when, so it is a promise with a name on it rather than decoration.

Before photo + what changed + after photo + the number that moved = one sheet

Why one page, and why a number

Most sites have a wall of before-and-after photos somewhere. Most of those walls get walked past, because a tidy corner says nothing about whether the work got easier, safer or faster. The poster sums up the alternative: Two photographs and a measured number beat a hundred words.

One page forces you to pick the one change and the one measure that matter. The number turns a nice picture into evidence that someone else can check, copy to another area, or challenge.

What goes on the sheet

A worked example, with the arithmetic

Here is an illustration from a packing area. At bench 3, the tape gun, knife and label rolls lived in a shared drawer under the next bench, and packers walked over and searched for them several times a shift. The team photographed the bench as it was, then fitted a shadow board at the bench with a marked place for each item.

To measure it, the lead timed the "fetch supplies" step with a stopwatch ten times before the change and ten times after, and the packer counted how often they fetched supplies in a shift: 40 times.

MeasureBeforeAfterChange
Total of 10 timings412 s186 s−226 s
Average per fetch41.2 s18.6 s−22.6 s (−55%)
Fetches per shift4040no change
Time fetching per shift1,648 s (27.5 min)744 s (12.4 min)−904 s (15.1 min)

Where each number comes from:

  1. Total of 10 timings: the ten stopwatch readings added up. 412 s before, 186 s after. The difference is 412 − 186 = 226 s.
  2. Average per fetch: the total divided by the 10 timings. 412 ÷ 10 = 41.2 s before, and 186 ÷ 10 = 18.6 s after.
  3. Change per fetch: 41.2 − 18.6 = 22.6 s saved. As a share of the before time, 22.6 ÷ 41.2 = 0.549, or about 55%.
  4. Fetches per shift: counted by the packer, 40. The change didn't alter how often supplies are needed, only how long it takes to get them.
  5. Time fetching per shift: average × fetches. Before: 41.2 × 40 = 1,648 s, and 1,648 ÷ 60 = 27.5 minutes. After: 18.6 × 40 = 744 s, and 744 ÷ 60 = 12.4 minutes. Saved: 1,648 − 744 = 904 s, and 904 ÷ 60 = 15.1 minutes a shift.

The proof line on the sheet reads: "Average time to fetch supplies: 41.2 s to 18.6 s (−55%)." It is short, it says what was measured, and anyone with a stopwatch can check it.

Be careful about stretching it further. If bench 3 runs five shifts a week, 904 × 5 = 4,520 s, which is 4,520 ÷ 60 = 75.3 minutes, about an hour and a quarter a week. Only write that if the bench really runs five shifts. Don't turn it into a yearly figure in money unless someone will stand behind every number in the calculation.

Four rules that keep the sheet honest

1. Shoot before you touch

The before photo is the one you cannot go back for. Take it the moment you decide to change something, before anyone tidies up for the camera.

2. Same spot, same angle

The pair only convinces if the frames match. Stand in the same place, at the same height, with the same zoom. A strip of tape on the floor where you stood makes the after shot easy. Don't crop one photo tighter than the other: a different crop can make a change look bigger than it is.

3. A number or an owner

The sheet will not publish on two photos and a paragraph - that is the point. Measure the same way before and after: same step, same method, enough timings to trust the average. If the result needs weeks to show, such as fewer damaged cartons, put up the sheet with a named owner and a date to measure it, and update it when the number is in.

4. Put it on the wall

Printed A4, dated, carrying your site's name. Post it near the SPQDC board or where the change was made, where the people who did it and the people who might copy it will both see it.

Where good sheets come from

Ideas for a sheet usually start on a gemba walk or from the team. A PICK chart helps choose which ideas to do first. When the problem is a repeat, a 5 Whys makes sure the change fixes the cause, and a bigger problem belongs on an A3, with the before and after sheet as its one-page result.

A free before and after poster

The Before & After poster from Lean Day Toolkit: four steps — before, photographed as found; fix it; after, same spot and same angle; the number that moved, or who owns the follow-up.

The Before & After poster has the four steps and four rules on one A4 page. It is free to download and print, and it is one of 19 free lean posters.

Before and after sheets in Lean Day Toolkit

Lean Day Toolkit has before and after sheets under Floor → Before and after, in the full version of the app. A sheet won't publish until it has an after photo, a description of what was done, dates in the right order, and either a measure with its before and after values or a follow-up action with an owner and a due date. The two photos are shown side by side at the same size, and neither is cropped differently from the other. Photo dates can be corrected, for pictures chosen from the gallery. The sheet prints as one landscape page, with a strip at the bottom that gives the measure, before to after, or the follow-up, its owner and due date.

← All articles