A PICK chart sorts improvement ideas by scoring each one for how much it helps (impact) and how hard it is to do (effort), and placing it in one of four boxes: Possible, Implement, Challenge or Kill. The ideas that help most and cost least land in Implement, and those are the ones you do first. It takes a few minutes per batch of ideas and turns a long suggestion list into a short to-do list.
High impact + low effort → Implement · Low impact + low effort → Possible · High impact + high effort → Challenge · Low impact + high effort → Kill
The four boxes
Draw a square and split it into four. Impact runs up the side, effort runs along the bottom. Some charts swap the axes, so always label them.
| Low effort | High effort | |
|---|---|---|
| High impact | Implement: do it now | Challenge: worth it, but plan it |
| Low impact | Possible: do it when there's time | Kill: say no, and say why |
How to score an idea
Use a 1 to 5 scale for each, as the Lean Day Toolkit poster does. Keep the meaning simple and agreed:
- Impact 1–5: how much it improves safety, quality, delivery or cost on the floor. A 5 removes a problem that hits every shift; a 1 is nice to have.
- Effort 1–5: time, money and people needed. A 1 is something the team can do this week with what it has; a 5 needs a budget, a contractor or a shutdown.
Decide where the middle line sits before you start. In the example below a 3 counts as high impact and as low effort, so a 3/3 idea lands in Implement rather than sitting on the line. Whatever rule you choose, use the same one every time.
Score as a small group, quickly. If two people disagree by more than one point, talk for a minute about what they each know; one of them usually knows something the other doesn't. Don't spend longer scoring an idea than it would take to do it.
A worked example
A packing team collected nine ideas over two weeks. These are illustrations, but they are the kind of ideas a packing area produces.
| Idea | Impact | Effort | Box |
|---|---|---|---|
| A tape dispenser at every bench instead of one shared | 4 | 1 | Implement |
| Add the film tension setting to the wrapper changeover checklist | 4 | 1 | Implement |
| Shadow board for knives and spare blades at the wrapper | 3 | 2 | Implement |
| Bigger print on rack location labels | 2 | 1 | Possible |
| Color-code pallet tickets by customer | 2 | 3 | Possible |
| A conveyor from packing to the wrapper instead of a hand truck | 5 | 5 | Challenge |
| A second label printer for line 2 | 3 | 4 | Challenge |
| Replace the canteen notice board with a screen | 1 | 4 | Kill |
| Move the packing area 10 m nearer the dock | 2 | 5 | Kill |
Using the rule above (impact 3 or more is high; effort 3 or less is low), the count is: Implement 3, Possible 2, Challenge 2, Kill 2. That adds up to 9.
Check the borderline ones. The shadow board has impact 3, which counts as high, and effort 2, which is low, so it goes in Implement. The pallet tickets have effort 3, which still counts as low, but impact 2, which is low, so they go in Possible. The label printer has impact 3, which is high, but effort 4, which is high, so it goes in Challenge.
What happens next
- Implement: all three are done within the week, each with an owner. Do them in order of impact, and break ties by lowest effort first. The tape dispensers and the checklist line (both 4/1) go first, then the shadow board (3/2).
- Challenge: the conveyor is the biggest idea on the list. It deserves a proper look at cost and payback, which is what an A3 is for. The label printer gets a quick check: how many minutes a week does the shared printer actually cost?
- Possible: the bigger labels can be done on a quiet afternoon. Keep them on the list.
- Kill: say no, out loud, to the person who suggested it, with the reason. A "no" with a reason keeps people suggesting. An idea that just disappears doesn't.
Measure the change
The poster's advice is Before and after, on one number.
Pick the measure when you
start: seconds per carton, steps walked per order, minutes lost to the wrapper per shift.
Then measure it again after the change.
For example, if packers walked to the shared tape dispenser 30 times a shift and each trip took 20 seconds, that is 30 × 20 = 600 seconds, or 10 minutes a packer per shift. If the trips drop to zero, those 10 minutes come back. Write down both numbers. "We saved 10 minutes per packer per shift" is what gets the next idea taken seriously.
Close the loop
When an idea is done, go and tell the person who raised it. The poster says it plainly:
An idea list nobody acts on teaches people to stop having ideas.
Telling people that their idea
was done, and thanking them by name, often matters more to the scheme than the chart itself. Many ideas come
up on a gemba walk, so the walk back to say thank you fits
naturally into the next one.
Common mistakes
- Scoring everything as a 3. The chart becomes one cloud in the middle. Push people to choose.
- Doing the Challenge ideas first because they're exciting. A month of easy wins builds the trust and the time to tackle the big ones.
- Never killing anything. A list that only grows looks like nothing gets done.
- Plotting and stopping. The chart is a decision, not a decoration. Every Implement idea needs an owner and a date.
A free ideas and PICK chart poster

The Ideas poster has the four steps, capture it, the 2×2, do the easy wins and close the loop, on one A4 page. It is free to download and print, and it is one of 19 free lean posters.
Ideas and the PICK chart in Lean Day Toolkit
Lean Day Toolkit has kaizen ideas and the PICK chart under Floor → Ideas, in the full version of the app. You capture an idea with a title and an impact and effort score from 1 to 5. Both scores start at 3, which puts an unscored idea in Implement. The chart puts impact up the side and effort along the bottom, and a 3 counts as high impact and as low effort, the same rule as the example above. Each idea is a dot you can tap to open, and each box shows its count. Each idea records who raised it, its stage (New, In progress, Done) and a before and after on one named measure, with the change worked out. When an idea with a name on it is done, the app prompts you to tell that person and records that you did. The PICK chart also prints on one A4 page with the ideas listed under it by box.