Process cycle efficiency (PCE) is the share of total lead time spent on work the customer would actually pay for. You calculate it by adding up the value-added time and dividing it by the lead time, from start to finish, waiting included. The first honest answer is almost always small, often under ten percent. That is not a failure. It shows you where the time goes, and it is nearly always the waiting.
PCE = value-added time ÷ total lead time × 100%
What counts as value-added
A step adds value when it changes the product or service in a way the customer wants and
would pay for, and it is done right the first time. Cutting, bending, coating and assembling
usually qualify. The poster's advice is to be harsh: Moving it, checking it, storing it - the
customer pays for none of it.
Some steps can't be skipped but still don't add value: an inspection, a safety check, the paperwork a regulator requires. Call these necessary non-value-added. Keep doing them and try to make them smaller, but don't count them as value just because they are required. If you do, the number looks better and stops telling you anything.
What lead time means here
Lead time is the clock time from the start of the process to the end: from order to door, or from raw material to finished product. It is not the sum of the busy steps. A pallet parked on the dock overnight is part of the lead time, so it goes on the list as a step of its own, with its minutes. Use the same clock for every step. In the example below, everything is in clock minutes, nights included.
How to calculate it, step by step
- List the steps. Everything between start and finish, including every wait, move and check. Walk the process if you can rather than working from memory.
- Time each one. Use measured times for the work steps, and real clock time for the waits: when the job arrived and when it left.
- Mark the value. For each step, ask: would the customer pay for this?
- Divide. Add up the value-added minutes and divide by the total of all the minutes.
A worked example
This is an illustration: an order for 20 steel brackets going through a small fabrication shop.
| Step | Minutes | Value-added? |
|---|---|---|
| Order waits in the inbox to be released | 240 | No (waiting) |
| Program the laser, print the paperwork | 15 | No |
| Wait for the laser | 480 | No (waiting) |
| Laser cut | 12 | Yes |
| Move to the press brake | 5 | No |
| Wait at the press brake | 300 | No (waiting) |
| Bend | 8 | Yes |
| Inspect | 10 | No (necessary) |
| Wait for the next powder-coat batch | 1,440 | No (waiting) |
| Powder coat | 20 | Yes |
| Pack | 5 | No |
| Wait for the truck | 180 | No (waiting) |
- Value-added time: 12 + 8 + 20 = 40 minutes.
- Lead time: 240 + 15 + 480 + 12 + 5 + 300 + 8 + 10 + 1,440 + 20 + 5 + 180 = 2,715 minutes, or about 45 hours (2,715 ÷ 60 = 45.25).
- PCE: 40 ÷ 2,715 = 0.0147, or about 1.5%.
Now split up the 2,675 minutes that are not value-added (2,715 − 40 = 2,675):
- Waiting: 240 + 480 + 300 + 1,440 + 180 = 2,640 minutes.
- Other non-value-added work: 15 + 5 + 10 + 5 = 35 minutes.
- Check: 2,640 + 35 = 2,675. With the 40 value-added minutes that makes 2,715.
The waiting is 2,640 ÷ 2,715 = 97.2% of the lead time. The poster's line is Ninety-five
percent of lead time is waiting. Start there.
Here it is even more.
Attack the gap, not the work
Look at what happens when the shop changes the waits and leaves the work alone.
- Powder coat twice a day instead of once. The batch wait falls from 1,440 to 480 minutes, saving 960. Lead time: 2,715 − 960 = 1,755 minutes. PCE: 40 ÷ 1,755 = 2.3%.
- Release orders every hour instead of twice a day. The inbox wait falls from 240 to 30 minutes, saving 210. Lead time: 1,755 − 210 = 1,545 minutes. PCE: 40 ÷ 1,545 = 2.6%.
The lead time has gone from about 45 hours to about 26 (1,545 ÷ 60 = 25.75), and nobody
worked any faster. Compare that with halving the laser cut from 12 minutes to 6: lead time only
drops by 6 minutes, to 2,709, and PCE actually falls to 34 ÷ 2,709 = 1.3%, because there is
less value-added time on top of the division. As the poster says, The value minutes rarely
need to get faster. The gaps between them do.
That last point is also a warning. PCE is a way to see the waiting, not a score to push up for its own sake. Track the lead time beside it.
Common mistakes
- Leaving out the waits. If you only list the work steps, PCE comes out close to 100% and means nothing. The gaps are steps too.
- Counting necessary checks as value. Inspection and paperwork stay non-value-added, even when you have to do them.
- Mixing clocks. Don't count the waits in working hours and the lead time in calendar hours. Pick one and use it for every step.
- Measuring once.
PCE is a trend, not a trophy.
Walk the process again after every change.
A free value or waste poster for the board

The Value or Waste poster puts the four steps, list the steps, mark the value, the ratio and attack the gap, on one A4 page. It is free to download and print, and it is one of 19 free lean posters. The eight wastes help when you are deciding what to mark as non-value-added.
Process cycle efficiency in Lean Day Toolkit
Lean Day Toolkit has a VA / PCE tool under Tools → VA / PCE, which is part of the full version. You list the steps with their minutes, mark each one VA or NVA, and the PCE percentage updates as you go. It also shows the value-added minutes against the lead time, and names the biggest single waste. The add-a-step card reminds you that the gaps are steps too. If you have already run a step-by-step time study, you can load it straight in, with its measured times and value-added marks, instead of typing them again.