Cycle time, lead time and takt time: what's the difference?

Takt is calculated, cycle time is measured at one step, and lead time includes all the waiting. One worked example, with Little's Law step by step.

· 4 min read · Plapl Games

Takt time is the pace the customer needs, cycle time is how long one step actually takes, and lead time is how long one unit spends in the whole process, from start to finish. Takt is calculated from demand, cycle time is measured with a stopwatch at one step, and lead time is measured across all the steps, including every minute the unit spends waiting between them.

Takt = time available ÷ demand · Cycle time = measured at the step · Lead time = work in progress ÷ throughput

The three side by side

Takt timeCycle timeLead time
Question it answersHow often must a unit be finished?How long does this step take?How long does one unit take to get through?
Where it comes fromCalculatedMeasured at one stepMeasured across the process, or worked out from the work in progress
Includes waiting?Not applicableNoYes, all of it
What changes itDemand or time availableHow the step is doneMostly how much work is waiting between steps

A note on words: some places use "cycle time" to mean the gap between finished units leaving the end of the line. Here it means the time one step takes for one unit. Agree on one meaning before you compare numbers, because the two can be very different.

One worked example, all three numbers

This is an illustration: a small fabrication cell making steel brackets in three steps (cut, bend, weld). It runs one 8-hour shift and has to ship 300 brackets a day.

1. Takt time

  1. 8 hours is 480 minutes. Take out 30 minutes of planned breaks: 450 minutes.
  2. 450 minutes × 60 = 27,000 seconds.
  3. 27,000 seconds ÷ 300 brackets = 90 seconds a bracket.

The cell has to finish a bracket every 90 seconds. The working is in how to calculate takt time.

2. Cycle time

Each step was timed for ten cycles at the machine. The averages:

StepCycle time (s)Against 90 s takt
Cut7020 under
Bend855 under
Weld8010 under

The last column is takt minus the step's cycle time. Every step keeps up. Bending is the slowest and so the bottleneck: running flat out it could make 27,000 ÷ 85 = 317.6, or 317 brackets a shift, against 300 needed. A time study is how you get these numbers.

3. Lead time

Now count everything inside the cell at one moment: 50 cut blanks waiting at the press brake, 67 bent brackets waiting at the welder, and 3 being worked on, one at each machine. That makes 50 + 67 + 3 = 120 brackets in progress.

Little's Law, proved by John D. C. Little in a 1961 paper in Operations Research, connects the three things you can count:

Lead time = work in progress ÷ throughput

  1. Throughput: the cell actually ships 300 brackets in 450 minutes. 300 ÷ 450 = 0.667 brackets a minute, or one every 450 ÷ 300 = 1.5 minutes.
  2. Work in progress: 120 brackets.
  3. Lead time: 120 ÷ 0.667 is the same as 120 × 1.5 = 180 minutes.

A blank cut now leaves the welder about three working hours later. Check it the simple way: put a strip of colored tape on one blank, write down the time, and note when it comes out of the weld. If the answer is far from 180 minutes, recount the work in progress.

What the three together tell you

Add up the cycle times and you get the time someone is actually working on the bracket: 70 + 85 + 80 = 235 seconds, just under 4 minutes. The lead time is 180 minutes, or 180 × 60 = 10,800 seconds. 235 ÷ 10,800 = 2.2%. That ratio is process cycle efficiency, and the other 97.8% is waiting.

That changes where you look. Making the bend 10 seconds faster wouldn't shorten the three hours much. Shrinking the piles would. Cap the work in progress at 30 brackets, and with the same 1.5 minutes between finished units, lead time becomes 30 × 1.5 = 45 minutes. Takt is the same, every cycle time is the same and so is the output, but the brackets get through four times faster.

There is one condition. Throughput only stays at 1.5 minutes a bracket if the bottleneck never runs out of work, so keep a small, deliberate buffer in front of the press brake and cut the rest.

Common mistakes

Takt, cycle time and lead time in Lean Day Toolkit

In Lean Day Toolkit, the takt calculator (Tools → Takt) and the stopwatch for quick time studies are among the tools that stay free. Every time study compares itself to takt: green under, red over. The VA / PCE tool, under Tools → VA / PCE, shows how many minutes of value add sit inside the lead time. It is in the full version. The glossary in the free learning section has a short entry for each of the three: takt time, cycle time, and lead time and PCE.

← All articles