Value stream mapping: how to draw a current-state map in a day

Walk the flow from shipping back, count the piles, time each step and add it up. A plan for one day and a worked example with lead time and value-add time.

· 5 min read · Plapl Games

A current-state value stream map is a one-page drawing of how one product family really flows today: every process step, the inventory between steps, and the information that tells each step what to make. You can draw one in a day by walking the flow from shipping back to receiving, counting inventory and timing each step as you go, then adding up the lead time and the value-add time along the bottom.

Days of inventory = units waiting ÷ daily demand  ·  Lead time ≈ sum of inventory days + process times

Where it comes from

The method was set out by Mike Rother and John Shook in Learning to See, published by the Lean Enterprise Institute in 1998. It is based on Toyota's material and information flow diagrams. Its main point is to look at the whole flow of a product rather than one machine at a time, because most of a product's lead time is spent waiting between steps, not being worked on.

Before the day

A plan for the day

  1. Morning: walk the whole flow once, quickly. Start at shipping and go backward toward receiving, as Learning to See recommends. That way you follow what the customer pulls. Just look at this point.
  2. Late morning: walk it again and collect data. At each step, write a data box: cycle time, changeover time, uptime, number of operators and shifts. Time a few cycles yourself rather than copying the routing (see time study). Count the inventory in front of each step: actual pieces, not the number in the system.
  3. After lunch: draw it. Customer at top right, supplier at top left, process boxes along the middle, triangles for inventory with the count under each, and the information flow (orders, schedules, forecasts) across the top.
  4. Mid-afternoon: draw the timeline. Along the bottom, convert each inventory count to days and write it on the upper step of the timeline. Write each step's cycle time on the lower step. Add up both.
  5. End of day: mark the problems. Put a "kaizen burst" on each obvious problem: the biggest pile, the step slower than takt, the long changeover. These become the start of the future-state map and the next kaizen event.

A worked example

This is an example, not real data. A small shop makes steel brackets in four steps: cut, bend, weld and paint. The customer takes 200 brackets a day. The shop runs one shift with 7.5 hours of working time, which is 27,000 seconds.

WhereUnits countedDays of inventoryCycle time (s)
Raw steel, before cut1,0001,000 ÷ 200 = 5
Cut40
Between cut and bend600600 ÷ 200 = 3
Bend55
Between bend and weld400400 ÷ 200 = 2
Weld120
Between weld and paint300300 ÷ 200 = 1.5
Paint90
Finished goods500500 ÷ 200 = 2.5

How to read the table. Units counted are the brackets found waiting at each place on the walk. Days of inventory is that count divided by the 200 a day the customer takes: how long a bracket arriving now would wait there. Cycle time is the typical time one bracket spends being worked on at each step, timed on the walk.

Lead time

Add up the inventory days: 5 + 3 + 2 + 1.5 + 2.5 = 14 days. The processing time of 305 seconds (below) adds very little to that, so the lead time is about 14 working days. A bracket bought as steel today ships in about three weeks.

Value-add time

Add up the cycle times: 40 + 55 = 95, + 120 = 215, + 90 = 305 seconds, or 5 minutes and 5 seconds of actual work.

How much of the lead time is work

  1. 14 working days × 27,000 seconds = 378,000 seconds.
  2. 305 ÷ 378,000 = 0.0008, or about 0.08%.

That ratio is process cycle efficiency. A very low figure like this is normal on a first map. It means the place to improve is the waiting between steps, not the speed of the steps. See cycle time vs lead time for why the two get confused.

Compare with takt

Takt = 27,000 ÷ 200 = 135 seconds. Weld, at 120 seconds, is the closest to it, with 15 seconds to spare. Weld has the least spare capacity, so time lost there is the hardest to make up. Weld gets a kaizen burst, and so does the 5 days of raw steel.

Common mistakes

A spaghetti diagram is useful alongside the map. It shows how far people and parts travel inside each step, which the value stream map doesn't.

A poster that goes with it

The VA / PCE poster covers the value-add and lead-time arithmetic at the bottom of the map. It is free to download and print.

Value stream maps in Lean Day Toolkit

Lean Day Toolkit has a diagram editor with a value-stream starter template, in the full version. The editor is in English only. The VA / PCE tool, also in the full version, adds up the value-add time and the total lead time and divides one by the other. The line map draws each station with its operators and one cycle time: the measured one from a study when there is one, otherwise the typed standard. It also draws WIP and finished-goods points and rework loops. The takt calculator stays free.

← All articles