Jidoka means that work stops at the first defect, so that a bad part is never passed on to the next step. The stop is short and planned. It costs a few minutes, while a defect that travels downstream can cost hours of sorting, rework and waiting. It is one of the two pillars of the Toyota Production System, and just-in-time is the other.
Detect the problem → stop → fix the condition → fix the cause
Where it comes from
The idea is older than the car company. Sakichi Toyoda, whose family business became Toyota, designed looms that stopped by themselves when a thread broke. Before that, one weaver watched one loom, because a broken thread left unnoticed meant yards of bad cloth. Once the loom stopped itself, one person could look after many machines and only had to step in when something went wrong.
Taiichi Ohno later described jidoka as "automation with a human touch". The machine, or the person, can tell normal from abnormal and stops when something is abnormal. On an assembly line the stop is usually human. Toyota lines have a cord or button that any operator can use to signal a problem, which is the andon.
The four steps
- Detect. Someone or something notices that the work is not normal: a gauge fails, a part doesn't fit, a label is wrong. This only works if "normal" is defined, which is what standard work and visual standards are for.
- Stop. The station stops making more of the same defect. Stopping is the operator's right and duty, and no one should be blamed for it.
- Fix the condition. The team leader arrives and gets the station running safely again: resets the jig, changes the worn tool, quarantines the suspect parts.
- Fix the cause. Later, often the same day, the team asks why it happened, using a 5 Whys or a fishbone, and puts in a countermeasure so it can't happen again. Often that countermeasure is a poka-yoke.
Step 3 without step 4 is firefighting: the line restarts, and the same stop comes back next week.
A worked example: what passing it on costs
This is an illustration with round numbers, not data from a real site. A drilling station makes steel brackets at one bracket every 30 seconds. At 9:00 the drill fixture slips, and the hole starts landing out of tolerance. The next check is at assembly, which collects the brackets an hour later.
If the defect is passed on:
- One hour is 60 × 60 = 3,600 seconds.
- At one bracket every 30 seconds, the station makes 3,600 ÷ 30 = 120 bad brackets before assembly finds them.
- Say each one takes 1.5 minutes to sort, re-drill and re-check. That is 120 × 1.5 = 180 minutes of rework.
- The fixture still has to be fixed. Say that takes 15 minutes, so the total is 180 + 15 = 195 minutes.
If the operator stops at the first defect:
- The operator gauges every bracket, so the first bad hole is found on the first bad bracket.
- The station stops and the fixture is reset: the same 15 minutes.
- One bracket needs rework: 1 × 1.5 = 1.5 minutes.
- The total is 15 + 1.5 = 16.5 minutes.
| Pass it on | Stop at the first defect | |
|---|---|---|
| Bad brackets made | 120 (3,600 s ÷ 30 s) | 1 |
| Rework at 1.5 min each | 180 min (120 × 1.5) | 1.5 min (1 × 1.5) |
| Fixing the fixture | 15 min | 15 min |
| Total time lost | 195 min | 16.5 min |
The fixture costs 15 minutes either way. Stopping only changes how many bad parts you make before you fix it. The table also leaves out the assembly team waiting for good brackets, the steel that can't be saved, and the risk that a bad bracket gets past the sorting and reaches the customer.
Why stopping feels wrong, and what to do about it
Most floors are measured on output, so a stopped machine looks like the worst thing that can happen. Three things help people trust the stop:
- Make the response fast. A stop that brings a team leader in two minutes feels like help. A stop that brings nobody for twenty minutes teaches people not to stop.
- Never blame the person who stopped. Thank them. The first time someone is told off for stopping is the last time anyone stops.
- Count stops as information. Log each one with its cause. A Pareto chart of a month's stops shows which countermeasures will remove the most of them, and downtime tracking keeps the stop time visible instead of hidden in a slower rate.
How to start on one line
- Pick one defect that travels. Choose one that is usually found downstream, at assembly, at packing or by the customer. Your first pass yield figures show where the rework piles up.
- Move the check to where the defect is made. A go/no-go gauge at the station is better than an inspection at the end.
- Agree the stop rule. Write down when to stop, who to call and what the caller does while waiting, then post it at the station.
- Close each stop with a cause. If the same stop happens three times, it needs an A3 or an 8D, not another reset.
Expect more stops in the first few weeks. That isn't the line getting worse. You are seeing problems that were already there.
Jidoka in Lean Day Toolkit
Lean Day Toolkit has no andon or stop button. It helps with step 4, finding and fixing the cause. The 5 Whys tool stays free, and so does the action list, so the countermeasure from each stop gets an owner and a date and stays tracked. In the full version, "Defects from a recording" lets you pin each defect on video footage and export the video, which helps when the team needs to see where in the cycle the defect starts.