Standard work: how to write it with the people who do the job

Three parts — takt, sequence and standard WIP — agreed with the people at the job and kept where the work happens. A worked example and how to write one.

· 5 min read · Plapl Games

Standard work is the current best and safest way to do a job, agreed with the people who do it, written down and kept at the job. In the Toyota Production System it has three parts: takt time, the work sequence and standard work-in-process (WIP). You write it by watching and timing the job with the operators, agreeing the sequence together, and checking that it fits inside takt.

Standard work = takt time + work sequence + standard WIP

Why it matters

Without a standard there is no baseline. If three people do a job three ways, a problem could come from any of them, and every improvement argument comes down to opinion. With a standard, a problem is a gap between the standard and what happened, and you can see it.

A standard is not meant to be fixed forever. It is the best way the team knows today. When somebody finds a better way, you test it and change the standard. That is what makes kaizen stick.

The three parts

1. Takt time

The pace the customer needs: available time divided by demand. See how to calculate takt time. Standard work has to fit inside it.

2. Work sequence

The order of the steps, each with its time and its key points: the details that make the step safe, right or easy. Doing the same steps in the same order every time is what makes the times repeatable.

3. Standard WIP

The smallest number of parts that has to be in the process for the sequence to run smoothly: one in the fixture, one curing, one waiting for a test. Less than this and the operator waits. More than this and parts pile up and hide problems.

A worked example

This is an example, not real data. A kitting cell packs repair kits by hand.

Takt

  1. Shift: 8 hours = 480 minutes.
  2. Minus planned breaks of 30 minutes = 450 minutes = 27,000 seconds.
  3. Demand: 375 kits a shift.
  4. Takt = 27,000 ÷ 375 = 72 seconds a kit.

Sequence

The team leader and the two operators timed ten cycles of each step with a stopwatch at the bench. The time below is the typical (middle) value. How to run a time study covers the method.

#StepKey pointTime (s)
1Take an empty tray from the rackTop tray first, so the oldest stock goes first8
2Load the six partsLeft to right, same as the pick bins22
3Fit and tighten the four lid screwsHand-start each one so it doesn't cross-thread18
4Check the count against the photoEvery pocket full, nothing loose9
5Print and stick the labelLabel on the end, not the lid7
6Place on the outbound cartLabel facing the aisle4
Total work content68

Adding up the times: 8 + 22 = 30, + 18 = 48, + 9 = 57, + 7 = 64, + 4 = 68 seconds. That is 4 seconds under the 72-second takt (72 − 68 = 4). The job fits, with only a small margin, so any step that grows is worth looking at.

Standard WIP

Two kits: one tray being loaded and one being checked and labeled. If a third kit is waiting on the bench, something upstream or downstream has stopped, and the team leader should go and look.

How to write it with the people who do the job

  1. Go and watch. Stand at the job with the operators, not in the office. If people do it differently, watch each of them. The differences are where the best method is hiding.
  2. Time it together. Break the job into steps the operators recognize, and time several cycles of each. Let the operators see the numbers as you go.
  3. Agree the best sequence. Take the safest, most reliable way anyone does each step. Ask why at every difference. Often one person has a trick that nobody else knows about.
  4. Write the key points and the reasons. For each step, write what makes it right and why it matters. "Hand-start the screws, because a cross-threaded lid leaks" is easier to remember than a rule with no reason. This follows the Job Instruction method from the Training Within Industry program of the 1940s.
  5. Check it against takt. Add up the step times. If the total is over takt, the job can't keep up as written. Balance it across people, or remove waste first. See yamazumi line balancing.
  6. Put it on one page at the job. Use photos where you can: what right looks like and what wrong looks like. See visual standards.
  7. Try it for a week, then fix it. The operators run it and mark what doesn't work. Change the sheet, not the people.

Keeping it alive

Standard work only works if somebody checks that it is being followed and still makes sense. That check belongs in the team leader's own routine. See leader standard work and the gemba walk. When the job isn't being done to the standard, ask why the standard didn't work before assuming the person didn't follow it.

Common mistakes

Posters that go with it

The Takt poster and the Time Study poster cover the two numbers standard work is built on. They are free to download and print.

Standard work in Lean Day Toolkit

Lean Day Toolkit has a takt calculator and a stopwatch for quick time studies, and both stay free. Time studies in the app compare the measured cycles with takt. Step-by-step (element) time studies are in the full version. So are visual standards: a photograph of the correct state, three to six key points, and what good and not-good look like side by side, tied to an area or a machine. The app's glossary, which stays free with the rest of the learning section, has standard work in it.

← All articles