Muda, mura and muri: the three kinds of waste, with floor examples

Waste, unevenness and overburden. What each one looks like on a real floor, why chasing muda alone rarely holds, and a worked example of leveling a week.

· 4 min read · Plapl Games

Muda is waste, mura is unevenness and muri is overburden: three Japanese words from the Toyota Production System for what stops work from flowing. Muda is what you see, mura is usually what causes it, and muri is what it costs your people and machines. Teams that only remove muda often see it come back, because the unevenness and overload that made it are still there.

Mura (uneven) → muri (overloaded) → muda (wasted)

Muda: waste

Muda is any activity that uses time, space or money and adds nothing the customer would pay for. Taiichi Ohno listed seven kinds: overproduction, waiting, transport, over-processing, inventory, motion and defects. Many teams add an eighth, unused skills. Each has its own article in the eight wastes of lean.

Floor examples:

Muda is the easiest of the three to spot on a gemba walk, and a spaghetti diagram makes motion and transport hard to argue with.

Mura: unevenness

Mura is variation in the work: in volume, in mix or in timing. The work arrives in peaks and gaps instead of a steady stream. It often starts upstream of the floor, in how orders are booked, released or batched.

The fix for mura is leveling, which is called heijunka: spreading volume and mix evenly across the days or hours.

Muri: overburden

Muri is asking people or equipment to do more than they reasonably can: too fast, too heavy, too long or too awkward. It shows up as overtime, rushing, skipped checks, strain injuries and machines run past their rating.

Muri is a safety issue as well as a cost issue. Rushing is where near misses come from, so a rise in near-miss reports on peak days is worth reading as a muri signal.

How the three feed each other

Here is a typical chain. Uneven demand (mura) overloads the crew on peak days (muri). Rushed work makes defects and leaves the area in a mess, and on quiet days people wait (muda). Lean Day Toolkit's glossary puts it in one line: "Every heavy trailer booked for Monday is mura. Covering it with overtime is muri. Tuesday's waste log is the symptom."

This is why many practitioners suggest working on mura first. Once the load is level, a lot of the overburden and waste goes with it.

A worked example: leveling a week

This is an illustration. A packing crew can pack 800 cartons a day at a normal, safe pace (an example figure; you would get yours from a time study). The orders currently land like this:

DayCartons bookedAgainst 800 capacityWhat it causes
Monday1,200400 over (1,200 − 800)Overtime and rushing: muri
Tuesday600200 under (800 − 600)Idle time: muda (waiting)
Wednesday600200 underIdle time
Thursday600200 underIdle time
Friday600200 underIdle time

Step by step:

  1. Weekly total: 1,200 + 600 + 600 + 600 + 600 = 3,600 cartons.
  2. Monday is 400 cartons over capacity, so the crew works overtime or rushes.
  3. Tuesday to Friday each have 200 cartons of spare capacity: 4 × 200 = 800 cartons of capacity that the crew is paid for and doesn't use.
  4. Leveled, the week is 3,600 ÷ 5 = 720 cartons a day.
  5. 720 is under 800 every day, which leaves 800 − 720 = 80 cartons of room each day for problems, with no overtime.

The total work is the same 3,600 cartons. Leveling only changes when it arrives, and that one change removes the Monday overload and half of the idle time. In practice the change is usually a conversation with whoever books the deliveries, not a change on the floor.

Where to start

Muda, mura and muri in Lean Day Toolkit

Lean Day Toolkit explains muri and mura in its glossary, which is part of the learning content and stays free. The waste log, where you record each piece of muda and see what keeps happening, is in the full version. Its tile on the Floor screen is subtitled "DOWNTIME + Pareto". The free printable eight wastes poster is a good one to put up next to the waste log.