PDCA: how to run Plan-Do-Check-Act on a real problem

Predict the result, try one change small, check it against the prediction, then keep it or drop it. The four steps done properly, a worked example, and the step most floors skip.

· 5 min read · Plapl Games

PDCA (Plan-Do-Check-Act) is a loop for testing one change at a time: you plan the change and write down what you expect it to do, try it on a small scale, check the result against what you expected, then act by making it the standard or dropping it. Then you go round again with the next change. Most improvement methods on the floor, from an A3 to a kaizen event, are this loop in a different shape.

Plan (predict) → Do (small) → Check (against the prediction) → Act (keep or drop) → round again

Where it comes from

The cycle grew out of Walter Shewhart's work on quality control at Bell Laboratories, and W. Edwards Deming taught a version of it to Japanese managers in 1950, and Japanese managers turned that into PDCA. That is why you will also hear it called the Shewhart cycle or the Deming cycle. Deming himself later preferred "Plan-Do-Study-Act", PDSA, because "check" sounded to him like inspection rather than learning. The idea is the same either way: a change is an experiment until the numbers say otherwise.

The four steps, done properly

Plan: predict before you change anything

State the problem with a number: "Changeovers on line 2 take 42 minutes on average." Understand why it happens before choosing a fix. A 5 Whys, a Pareto chart or a gemba walk are the usual ways in. Then pick one change and write down the prediction: what will move, by how much, and when you will check. Writing the number down first is the whole trick. It stops anyone quietly redefining success afterward.

Do: one change, small

Try it on one line, one shift or one cell, for long enough to get a handful of results. Change one thing only. Move the bench, retrain the team and change the label in the same week, and if it gets better you won't know which one did it. Write down what actually happened, including anything that didn't go to plan.

Check: against the prediction, not a feeling

Compare the results with the number you wrote down. Look at the bad results as well as the average; they usually tell you what the next loop should be. This is the step that gets skipped, because plan and do feel like progress and check feels like paperwork. Without it you are just changing things.

Act: keep it or drop it

If it worked, make it the standard: update the work instructions, put up a visual standard, record it on a before and after sheet, and spread it to the next area. If it didn't, undo it and write down why. Dropping a change is a valid result, and it stops the next person trying the same thing.

A worked example

This example is invented for illustration. A team leader times changeovers on line 2, from the last good part of one job to the first good part of the next.

Plan. The last 10 changeovers averaged 42 minutes. Watching two of them showed the operator walking to the tool crib for wrenches and fixtures after the line had stopped. The change: load a cart with the next job's tools and fixtures before the line stops. The prediction, written on the board: "Average under 30 minutes over the next 8 changeovers. Check on Friday of week 2."

Do. Line 2 only, for two weeks, timed with a stopwatch. Eight changeovers:

ChangeoverMinutesNote
131A wrench missing from the cart; operator went to the crib
228
327
433The same wrench missing again
526
629
725
828
Total227Sum of the eight times
Average28.4227 ÷ 8 = 28.375, rounded

Check. Each figure in the minutes column is the stopwatch time for one changeover. They add up to 227 (31 + 28 + 27 + 33 + 26 + 29 + 25 + 28), and 227 ÷ 8 gives an average of 28.4 minutes. The prediction was under 30, so it held. Against the old average, 42 − 28.4 = 13.6 minutes saved per changeover, about a third (13.6 ÷ 42 = 0.32).

The two slow ones matter more than the average. Both were over 30, and both had the same cause: a wrench that wasn't on the cart. Without them, the other six add up to 163 minutes (28 + 27 + 26 + 29 + 25 + 28), and 163 ÷ 6 = 27.2 minutes.

Act. The cart becomes the standard for line 2, with a shadow board so a missing wrench shows as an empty outline before the line stops. Loading the cart goes into the team leader's standard work. The next loop tries the same cart on line 3, and a date goes on the calendar to time line 2 again in a few months, when nobody is watching it anymore. For more on cutting changeovers, see SMED.

Common mistakes

Where PDCA shows up on the floor

An A3 is a PDCA written on one page. A kaizen event runs the loop quickly, over a few days. The weekly review is a natural place for the check: put the open changes on the agenda, with their predictions next to the results.

PDCA in Lean Day Toolkit

Lean Day Toolkit doesn't have a separate PDCA form. Its glossary explains PDCA and links straight to the action list. The action list is free and has reminders, and each action can carry an owner and a due date, which is where the "check on Friday" goes.

The free Learn section has an animated lesson, "PDCA", and a narrated film, "The loop under everything". The A3 tool, which runs the same loop on one page, is in the full version.

← All articles