Heijunka means leveling production. Instead of making each product in a big batch when the schedule suits it, you spread both the volume and the mix of products evenly across every working day. You take the average demand, split each day in the same proportions as the orders, and run a short pattern that repeats, so Tuesday looks like Monday.
Weekly demand ÷ working days = daily volume → split it by the product mix → repeat the same pattern every day
Where it comes from
Heijunka is Japanese for leveling, and it is one of the foundations of the Toyota Production System. Toyota's own account of that system names three things to remove: muda (waste), muri (overburden) and mura (unevenness). Heijunka is the tool aimed at mura. When the work coming into a line swings up and down, people and machines are overloaded one day and waiting the next, and both show up as waste. Leveling the input stops the swings at the source, so you aren't chasing them on the floor.
The eight wastes are what you see. An uneven schedule is often why they are there.
Why big batches hurt
Running one product all day and another tomorrow feels efficient, because you change over less. But it moves the problem somewhere else:
- Customers wait. An order for the product you made on Monday waits until next Monday.
- Upstream gets whiplash. Parts for each product are needed in a rush on one day and not at all on the others, so suppliers and feeder cells hold stock for the peak.
- Stock piles up. You keep a week of each product in finished goods to cover the gaps between runs.
- Problems hide. A fault in a product you only make on Fridays is found a week later, in a pile of 50.
A worked example
This example uses made-up but realistic numbers. A small cell makes three versions of a bracket, A, B and C, on one shift, five days a week. This week's order book is 200 of A, 100 of B and 50 of C.
- Total volume: 200 + 100 + 50 = 350 brackets a week.
- Daily volume: 350 ÷ 5 days = 70 brackets a day.
- Daily mix: A is 200 ÷ 5 = 40 a day, B is 100 ÷ 5 = 20 a day, and C is 50 ÷ 5 = 10 a day. Check: 40 + 20 + 10 = 70.
- Takt time: the shift is 480 minutes with 30 minutes of planned breaks, which leaves 450 minutes, or 27,000 seconds. 27,000 ÷ 70 = 385.7 seconds, about one bracket every 6.4 minutes. See how to calculate takt time.
Here is the same week planned two ways: in batches and level.
| Product | Weekly demand | Batch plan | Level plan |
|---|---|---|---|
| A | 200 | Mon 70, Tue 70, Wed 60 | 40 every day |
| B | 100 | Wed 10, Thu 70, Fri 20 | 20 every day |
| C | 50 | Fri 50 | 10 every day |
Weekly demand is the example's order book. The batch plan fills the cell's 70 a day in product order. A takes Monday, Tuesday and the first 60 of Wednesday (70 + 70 + 60 = 200). B takes the last 10 of Wednesday, all of Thursday and the first 20 of Friday (10 + 70 + 20 = 100). C takes the last 50 of Friday. Every day still adds up to 70. The level plan is each weekly figure divided by 5.
Both plans ship 350 brackets. In the batch plan, a C order that arrives on Monday waits until Friday, and all the C parts are needed on one day. In the level plan, C is made every day, so no order waits more than a day for its turn.
Turn the mix into a pattern
The brackets ship in totes of 10. A day of 70 is 7 totes: 4 of A, 2 of B and 1 of C. Spread them through the day instead of grouping them:
A · B · A · C · A · B · A
The time allowed to make one tote is called the pitch: takt × pack size = 385.7 × 10 = 3,857 seconds, about 64.3 minutes. Check it against the day: 7 totes × 64.3 minutes = 450 minutes, the whole shift. So every 64 minutes, one tote of work is released to the cell, in that order, all day, every day.
The leveling box
Toyota made the pattern physical with a heijunka box. It is a rack of slots with one column for each pitch and one row for each product. Kanban cards go into the slots in the pattern. Each pitch, a material handler takes the next card and brings it to the cell. If a card is still in its slot when its pitch is over, the cell is behind, and everyone can see it. The box works together with a kanban pull system; it doesn't replace one.
Leveling volume as well as mix
Real orders move around from week to week. Say the last four weeks were 330, 370, 340 and 360 brackets. That is 1,400 in total, and 1,400 ÷ 4 = 350 a week. Plan to make 350 every week and let a small stock of finished brackets take up the difference. The highest week was 20 above the average and the lowest was 20 below, so about 20 brackets, split across A, B and C in the 4 : 2 : 1 mix, is a reasonable starting buffer. Review the average each month. When it moves, change the daily rate in planned steps, not day to day.
The catch: changeovers
Leveling costs changeovers. The batch week above changes over twice: A to B on Wednesday and B to C on Friday. The pattern A B A C A B A changes over six times a day, which is 30 a week.
Suppose each changeover takes 10 minutes. Six a day is 60 minutes, which leaves 450 − 60 = 390 minutes, or 23,400 seconds, to make 70 brackets. 23,400 ÷ 70 = 334.3 seconds, so to keep up the cell now has to make a bracket in about 334 seconds instead of 386. At 30 minutes a changeover, six a day take 180 minutes. That leaves 270 minutes (16,200 seconds), and 16,200 ÷ 70 = 231 seconds a bracket, which this cell may not manage.
That is why SMED usually comes before heijunka. If changeovers are still long, level in stages: make every product every other day first, then every day, then in the full pattern. Level at the bottleneck, because that is the step whose time really runs out.
Common mistakes
- Leveling the plan but not the release. If planning still drops a week of one product on the floor at once, the pattern exists only on paper.
- Changing the pattern every day. The point is a rhythm people can learn. Change it when average demand changes, not when one order does.
- No buffer. Without a small finished-goods stock, a busy week turns into late orders.
- Ignoring the work content. If C takes twice as long to build as A, check the balance with a yamazumi chart before you spread C through the day.
Heijunka and Lean Day Toolkit
Lean Day Toolkit has no heijunka planner. Its takt calculator, which gives you the takt time in step 4 of the worked example, is one of the tools that stays free. The learning section, also free, has short animated lessons called "Muri, mura, muda" and "Kanban and pull", the two ideas that heijunka sits between. The Takt poster covers the takt step on one page.