Kanban: how to size a simple two-bin or card system

Demand during the refill time, plus a margin, divided by what a container holds. Two worked examples, one two-bin and one card loop, with every number explained.

· 5 min read · Plapl Games

To size a kanban, work out how many parts are used while one container is away being refilled, add a safety margin, and that is the quantity the system has to hold. For a two-bin system it is the size of one bin. For a card system, divide it by the container quantity and round up to get the number of cards.

Number of cards = (daily demand × replenishment lead time × (1 + safety)) ÷ container quantity

What a kanban is

Kanban is Japanese for "signboard" or "card". In the Toyota Production System it is the signal that tells the earlier process to make or deliver more, and only that much. The empty bin or the returned card is the order. Nothing gets made or moved without one.

That gives you a pull system with a ceiling built in. The most stock that can ever be in the loop is the number of containers times what each one holds, so overproduction, the waste Taiichi Ohno called the worst of the wastes, has a limit.

The four numbers you need

Worked example 1: a two-bin system

This is an example, not real data. An assembly bench uses one kind of screw.

In a two-bin system, the bench works out of one bin while the second waits full behind it. When the first runs empty, the operator starts on the second and sends the empty one off. The second bin has to last until the first comes back.

  1. Demand during the lead time: 1,200 a day × 2 days = 2,400 screws.
  2. Add the safety margin: half a day is 1,200 × 0.5 = 600 screws.
  3. Bin size: 2,400 + 600 = 3,000 screws.
  4. In boxes: 3,000 ÷ 500 = 6 boxes per bin.

Most stock at the bench: two full bins, 6,000 screws, which is 6,000 ÷ 1,200 = 5 days of use. If that feels like a lot, the lever is the lead time, not the bin. A daily collection and same-day refill would bring the lead time to 1 day and the bin to 1,200 + 600 = 1,800 screws.

Worked example 2: a card loop

This is an example, not real data. A press makes brackets for an assembly line. Brackets move in totes of 50, and each tote carries a card.

  1. Demand during the lead time: 800 × 1.5 = 1,200 brackets.
  2. Add 10% safety: 1,200 × 1.10 = 1,320 brackets.
  3. Divide by the tote: 1,320 ÷ 50 = 26.4.
  4. Round up: 27 cards.

Most brackets in the loop: 27 × 50 = 1,350, which is 1,350 ÷ 800 = 1.7 days of use (1.69, rounded).

NowAfter a quicker changeover
Lead time1.5 days1 day
Demand × lead time800 × 1.5 = 1,200800 × 1 = 800
With 10% safety1,200 × 1.10 = 1,320800 × 1.10 = 880
÷ 50 per tote26.4 → 27 cards17.6 → 18 cards
Most stock in the loop27 × 50 = 1,35018 × 50 = 900

The right-hand column assumes the press team cuts the queue by changing over more often, which brings the lead time down to one day. That takes out 9 cards and 450 brackets (1,350 − 900 = 450) with no change in demand. See SMED changeover for how to shorten changeovers.

Rules that make it work

These are taken from Toyota's kanban rules as they are usually taught:

Common mistakes

Kanban and Lean Day Toolkit

Lean Day Toolkit has no kanban calculator. In the full version, the line map can show racks, WIP and finished goods next to the work stations, so the places where the loop holds stock are on the drawing. 5S audits and the action list, where you can track a card-count change to the end, both stay free.