A supervisor needs about five lean KPIs: one each for safety, people, quality, delivery and cost, the five letters of an SPQDC board. A good starting set is near misses reported, absenteeism, first pass yield, schedule attainment and OEE (or output per labor hour). Each one should be calculated the same way every day and reviewed at the board.
One letter, one measure, one standard, checked every day
What makes a KPI useful at team level
A KPI at the team's board has to pass three tests. The team can affect it this shift. It can be counted by the end of the shift without waiting for finance. And it has a written standard, so the day is clearly green or red. A monthly cost-per-unit figure fails the first two. It belongs in a manager's review, not at the huddle.
Also keep in mind the difference between lagging and leading measures. Injuries, scrap and late orders are lagging: they tell you what already happened. Near misses reported, actions closed on time and audits done are leading: they show whether the work that prevents problems is getting done. A good set has some of each.
The example shift
Example: every calculation below uses one packing line on one day shift. These are the numbers the team leader collects:
| Item | Value | Where it comes from |
|---|---|---|
| Planned production time | 435 min | 480-minute shift minus 45 minutes of planned breaks |
| Unplanned downtime | 45 min | Total of the downtime log for the shift |
| Ideal cycle time | 0.5 min (30 s) | The line's rated speed: one carton every 30 seconds |
| Cartons started | 690 | Counter at the start of the line |
| Cartons scrapped | 18 | Scrap bin count |
| Cartons reworked | 12 | Rework station tally |
| Cartons planned | 700 | Today's schedule |
| People on the line | 4 | Each paid for the 435 minutes of planned time |
Safety: near misses reported
Count the near misses and hazards reported this shift or this week, and how many of those have a closed action. More reports usually mean people trust the system, not that the area got more dangerous. See near-miss reporting.
Above team level, sites in the US usually also track OSHA's total recordable incident rate: recordable cases × 200,000 ÷ hours worked. The 200,000 is OSHA's figure for 100 full-time workers at 40 hours a week for 50 weeks. Example: 2 recordable cases in 180,000 hours worked gives 2 × 200,000 = 400,000, and 400,000 ÷ 180,000 = 2.22.
People: absenteeism
Absenteeism = shifts missed ÷ shifts scheduled
Example: a team of 6 people working 20 shifts each in a month is scheduled for 6 × 20 = 120 shifts. If 6 shifts are missed without being planned, absenteeism is 6 ÷ 120 = 0.05, or 5%. A cross-training count (how many people can run each station) is a good second measure for this letter.
Quality: first pass yield
First pass yield = units good the first time ÷ units started
Good the first time means neither scrapped nor reworked. From the example shift: 690 − 18 − 12 = 660 cartons were good the first time. 660 ÷ 690 = 0.9565, so first pass yield is 95.7%.
Leaving rework out of the count would give 672 ÷ 690 = 97.4%, which looks better and hides the 12 cartons someone had to fix. That hidden fixing is why first pass yield counts rework as a miss.
Delivery: schedule attainment
Schedule attainment = good units made ÷ units planned
From the example: 660 ÷ 700 = 0.9429, or 94.3%. Count only good units, and count against the plan as it stood at the start of the shift. If you rewrite the plan at noon to match what the line can make, the measure always reads 100%. During the shift, the hour-by-hour board shows the same comparison hour by hour, so a miss is visible by 9 a.m., not at the end of the day.
Cost: OEE, or output per labor hour
For a machine-paced line, use OEE. It multiplies three factors:
- Availability = run time ÷ planned time. Run time is 435 − 45 = 390 minutes. 390 ÷ 435 = 0.8966, or 89.7%.
- Performance = (ideal cycle time × units made) ÷ run time. 0.5 × 690 = 345 minutes of ideal running. 345 ÷ 390 = 0.8846, or 88.5%.
- Quality = good units ÷ units made. 660 ÷ 690 = 0.9565, or 95.7%.
- OEE = 0.8966 × 0.8846 × 0.9565 = 0.7586, or 75.9%.
Check it a second way: good units × ideal cycle time ÷ planned time = 660 × 0.5 ÷ 435 = 330 ÷ 435 = 0.7586. Same answer. The weakest of the three factors tells you where to look first, and the six big losses say what to look for.
For work paced by people rather than a machine, output per labor hour is simpler. Labor hours: 4 people × 435 minutes = 1,740 minutes, and 1,740 ÷ 60 = 29 hours. Output: 660 ÷ 29 = 22.8 good cartons per labor hour.
The set on one card
| Letter | KPI | Example result |
|---|---|---|
| S | Near misses reported, actions closed | A count, read week on week |
| P | Absenteeism | 6 ÷ 120 = 5% |
| Q | First pass yield | 660 ÷ 690 = 95.7% |
| D | Schedule attainment | 660 ÷ 700 = 94.3% |
| C | OEE (or output per labor hour) | 75.9% (or 22.8 per hour) |
Each result comes from the sections above. Mark each one green or red against a standard the team agreed on, on the SPQDC board, and read the trend in the weekly review.
Three ways KPIs go wrong
- Too many. Twelve measures on the board means none of them gets discussed. Keep one per letter at team level.
- Changing the formula. If the method changes month to month, the trend means nothing. Write the formula on the board.
- Used to blame. A KPI used against people gets gamed. It should start a 5 Whys, not an argument.
Lean KPIs in Lean Day Toolkit
Lean Day Toolkit has an OEE calculator and a takt calculator, and both stay free. The OEE calculator shows availability, performance and quality separately, with the formula for each, and points to the weakest one. The SPQDC board, the hour-by-hour board and downtime tracking are in the full version.