A swimlane process map is a flowchart split into horizontal lanes, one for each person, team or department, with every step of a job drawn in the lane of whoever does it. Each time the flow crosses from one lane to another, the job changes hands, and that is usually where it waits. Draw the map, count the crossings, put a wait time on each, and you know which handoffs to fix first.
Lanes = who · boxes = what · arrows across lanes = handoffs · time on each handoff = where the job waits
Why handoffs slow a job
Inside one lane, work usually moves straight on: the person who finishes a step starts the next one. At a handoff, the work goes into someone else's queue, inbox or tray. It waits there until they notice it, it may arrive missing information, and it sometimes comes back. Doing the steps rarely takes long. Waiting between them takes most of the time, which is why lead time is usually much longer than the time spent working.
An ordinary flowchart hides this, because it shows the steps but not who owns each one. Lanes make every change of owner visible.
How to draw one, step by step
- Pick one job, with a clear start and end. "From a guard being reported broken to the machine running safely again" is a job. "Maintenance" is not.
- List the people or teams involved. Each one gets a lane, drawn as a horizontal band with its name on the left. Four to six lanes is typical. If you need more than eight, the job is probably two jobs.
- Walk the job and write the steps. Follow a real example from start to finish, as you would on a gemba walk, and ask the people doing each step. Write each step as a verb and an object, such as "raise work order", and put it in its owner's lane.
- Join the steps with arrows in the order they happen. Draw decisions as diamonds, with one arrow for each answer.
- Mark every arrow that crosses a lane. Number them. These are the handoffs.
- Put two times on the map: the working time of each step and the waiting time at each handoff. Measure them on real jobs if you can. If you can't, write what people tell you and mark those times as estimates.
Use sticky notes on brown paper or a whiteboard first. It is easier to move a sticky note than to argue about a drawing.
A worked example
This example is made up: a broken machine guard, from report to repair, in a small plant. There are four lanes: operator, team leader, maintenance and stores.
- Operator: finds the broken guard and tells the team leader. (Handoff 1)
- Team leader: locks out the machine and raises a work order. (Handoff 2: to maintenance)
- Maintenance: reads the order, goes to look, and finds that a new hinge is needed. (Handoff 3: to stores)
- Stores: has no hinge and orders one. When it arrives, stores calls maintenance. (Handoff 4: back to maintenance)
- Maintenance: fits the hinge and asks the team leader to check it. (Handoff 5)
- Team leader: checks the guard, removes the lockout, and tells the operator to restart. (Handoff 6)
That is six handoffs for one hinge. The team timed one real case:
| Handoff | From → to | Wait (hours) | What the wait was |
|---|---|---|---|
| 1 | Operator → team leader | 0.5 | Team leader was in a meeting |
| 2 | Team leader → maintenance | 6 | Work order sat in the queue until the next shift's review |
| 3 | Maintenance → stores | 1 | Walk to stores and the request form |
| 4 | Stores → maintenance | 26 | Supplier delivery of the hinge |
| 5 | Maintenance → team leader | 2 | Team leader on another line |
| 6 | Team leader → operator | 0.5 | Restart and first-part check |
| Total | 36 | 0.5 + 6 + 1 + 26 + 2 + 0.5 |
The hands-on work was about 1.5 hours: 0.5 hours to inspect the guard and 1 hour to fit the hinge. The machine was down for 36 + 1.5 = 37.5 hours, so about 96% of that time (36 ÷ 37.5 = 0.96) was waiting at handoffs.
What to fix, and in what order
Start with the longest waits, not the most steps.
- Handoff 4 (26 hours): a hinge that breaks once can break again. Keep two in stores with a reorder point. The next time a guard breaks, this wait is close to zero.
- Handoff 2 (6 hours): guard faults are safety jobs. Agree that they go to maintenance by phone the same hour instead of waiting in the queue, and write that into the shift handover.
- Handoffs 3 and 4 together: if maintenance can take common spares from a small cabinet on the floor, the trip to stores and the request form go away.
Then draw the map again for the next case. Fixing the stock takes the 26-hour wait out of handoff 4. Moving a box from one lane to another often removes a handoff entirely, which is better than speeding it up.
Common mistakes
- Drawing the job as the procedure says. Map one real case, including the rework loops and the "we just phone Dave" shortcuts. Those are often where the time goes.
- Lanes by job title only. If the work goes to a shared inbox, draw the inbox as a lane. A queue that nobody owns is where jobs sit longest.
- No times. A map without times shows the shape of the process but not where the time goes. Even rough waits show which handoff to fix first.
- Mapping the whole plant. One job, one page. For the flow of material across a site, a value stream map is the right tool, and a spaghetti diagram shows walking.
Swimlane maps in Lean Day Toolkit
Lean Day Toolkit has a diagram editor with a swimlane starter template, alongside process flow, fishbone, value stream and spaghetti templates. Diagrams are in the full version, and the editor itself is in English only. When a handoff needs fixing, the action list, which stays free, can track who owns the fix and remind them.