Control charts for the shop floor: how to read one and when to react

Every process wobbles. A control chart tells you which wobbles are normal and which ones mean something changed. A worked example, three reaction rules, and the common mistakes.

· 5 min read · Plapl Games

A control chart is a run chart of one measurement with a center line and two limits worked out from the process's own past results, so you can see whether a new point is ordinary variation or a sign that something has changed. When a point lands inside the limits and the pattern looks random, leave the process alone. When a point falls outside them, or a clear pattern appears, go and find out what changed.

Limits = average ± 2.66 × average moving range (individuals chart)

Why a supervisor needs one

No process gives the same number twice. A filler puts slightly different weights into each bottle, and a changeover takes a few minutes more or less each time. If you react to every small move, adjusting the machine, retraining someone, or calling a meeting, you add variation instead of removing it. If you never react, you miss the day a real change started.

Walter Shewhart came up with the control chart at Western Electric and Bell Telephone Laboratories in the 1920s to separate those two cases. He called the everyday wobble chance causes and the signals assignable causes; W. Edwards Deming later named them common cause and special cause variation. The chart gives you a rule instead of a gut feeling.

A worked example: fill weight

Example: a bottle filler has a target of 500 g. Once an hour an operator weighs one bottle. These are ten readings from one shift. A real chart should start from at least 20 readings; ten keeps the arithmetic short here.

HourWeight (g)Moving range (g)
1502–
24984
35013
44992
55034
65003
74973
85014
95001
104991

The weight column is what the scale showed. The moving range is the difference between each reading and the one before it, ignoring the sign: hour 2 is 502 − 498 = 4, hour 3 is 501 − 498 = 3, and so on. Hour 1 has no moving range because nothing comes before it.

  1. The center line (the average): add the ten weights. 502 + 498 + 501 + 499 + 503 + 500 + 497 + 501 + 500 + 499 = 5,000 g. Divide by 10: 5,000 ÷ 10 = 500.0 g.
  2. The average moving range: add the nine ranges. 4 + 3 + 2 + 4 + 3 + 3 + 4 + 1 + 1 = 25 g. Divide by 9: 25 ÷ 9 = 2.78 g.
  3. The distance to each limit: 2.66 × 2.78 = 7.39 g. (2.66 is the standard constant for an individuals chart. It turns the average moving range into three standard deviations.)
  4. Upper control limit: 500.0 + 7.39 = 507.4 g.
  5. Lower control limit: 500.0 − 7.39 = 492.6 g.

Draw a line at 500.0, dashed lines at 507.4 and 492.6, and plot each new hourly reading as it comes in. As long as the weights stay between the dashed lines and wander up and down without a pattern, the filler is doing what it normally does.

When to react: three rules

Western Electric's Statistical Quality Control Handbook (1956) and, later, Lloyd Nelson's rules set out several signal patterns. Three cover most of what a supervisor needs:

1. One point outside a limit

Say the next four readings are 504, 505, 506 and 509 g. The 509 is above 507.4, so stop and ask what changed: a new batch of product, a worn valve, a different operator, or a setting someone touched. Look at it now, while the cause is still there to find.

2. A run on one side of the center line

Eight points in a row on the same side of the average is a signal even if every one of them is inside the limits. A filler that reads 501, 502, 501, 503, 502, 501, 502, 503 has shifted, and it is slowly giving product away.

3. A steady trend

Six points in a row each higher (or each lower) than the one before usually means something is drifting, like tool wear, temperature or a clogging filter. The 504, 505, 506, 509 above was already heading that way before it crossed the line.

If none of these appear, don't adjust. Changing a stable process in response to a single ordinary reading is called tampering, and it makes the spread wider.

Control limits are not specification limits

The specification (say 490 to 510 g) is what the customer or the label requires. The control limits (492.6 to 507.4 g) are what the process actually does. They answer different questions:

Never draw the specification limits and call them control limits. Never set control limits by choosing numbers that look reasonable. They come from the data.

Four mistakes to avoid

Other kinds of data

The individuals chart above suits one measurement at a time: a weight, a cycle time, a temperature. If you measure small groups (five parts every hour), an X-bar and R chart is the usual choice. If you count things, like defects per shift or late orders per day, there are p, np, c and u charts. The way you read them is the same: the center line, the limits, and the same three signals.

Lean Day Toolkit and control charts

Lean Day Toolkit does not draw control charts. Its stopwatch, which stays free, records cycle times at the job, and those readings are the kind of data an individuals chart is built from. See how to run a time study for how to collect them.